MAINTENANCE
E-5 E-5
POWER WAVE 450
RECOMMENDED TOOLS FOR INSTAL-LATION OR SERVICE OF COOLER:
absorbent towels
alcohol wipe
3 mm allen wrench (G3503 only)
socket wrench
4 inch long minimum socket extension
1/4, 5/16, and 3/8 hex standard depth sockets
5/32 allen socket
medium blade slotted screwdriver
large blade slotted screwdriver, 8 inches long
minimum
two 7/16 open or box end wrenches
one 7/8 open or box end wrench
needlenose pliers
two 10 inch long adjustable wrenches
wire cutter
molex pin removal tools
tape measure
small mechanics mirror
flashlight
dental pick
digital multimeter (DMM)
G3503-[ ] INSTALLATION OR SER-VICE TOOL USAGE
Fastener Usage Qty. Tool
Shroud to cooler base 4 all use 5/16 hex screw and 3/8 hex
Quick Disconnect (QD) bracket 2 nut.Relay may require large blade
Heat exchanger to cooler base 2 slotted screwdriver 8 in.long min.
Relay to cooler base 2
Screw to 4 3 mm allen wrench (G3503 only)
fasten reservoir to cooler base 5/16 Hex Socket (G3503-1 only)
Hose Clamp 10 1/4 hex or medium slotted screwdriver
Fan set screw 1 5/32 allen socket with wrench and 4
in.min. extension
Pump carbonator clamp screw 1 5/16 hex socket with ratchet wrench
Motor mounting bolts 4 two 7/16 open or box end wrenches
Motor access door 2 1/4 hex socket with wrench
Motor harness ground at motor 1 1/4 hex socket with wrench
terminals 2 needlenose pliers
relay terminals 1 and 2 2 large blade slotted screwdriver 8 in.
minimum long.
relay terminals 3 and 4 2 medium slotted screwdriver
All plumbing components N/R two 10 inch adjustable wrenches

REMOVING AND INSTALLING THE G3503-[ ]

COOLER

1.Preparation:
Always switch off the Power Wave machine
power.
Always disconnect the Power Wave machine
from service input power.
2.Remove cooler assembly G3503-[ ]:
a.remove gas cylinder(s) from tray.
b.remove cooler access panel.
c.Remove both fasteners from base that hold cool-
er in place. Remove ground lead, if present.
Carefully pull cooler assembly rearward, until
coolers Molex connectors are visible.
d.disconnect coolers connectors from the P3 and
P4 harnesses.Continue pulling the cooler out of
the Power Wave.
3.If necessar y, perform periodic maintenance or ser-
vice on the cooler.
4.Reinstall cooler by reversing tasks in step 2. Be sure
to reattach ground lead, if previously removed.
5.If necessar y, fill cooler with selected coolant to spec-
ified level (see Fig.1).
6.Attach desired water-cooled accessor y (gun and
wire feeder or TIG torch) to coolers QDs.
7.Reconnect ser vice input power to the Power Wave:
verify that the reconnect panel setting and lead
placement match the service voltage.
8.Pr ime the cooler:
a.Install the Set-up overlay.
b.Keep accessorieshose lengths horizontal,
either coiled or straight, and no higher than 4
feet of the specified coolant level (Fig.1).
c.Switch on the Power Wave machine.
d.Press the "WATER COOLERENABLE" button
so that the "WATERCOOLER ENABLED" light
is illuminated .
e.Press the "PRIME WATER COOLER" button
until the "WATERCOOLER PRESSURE" light is
steadily illuminated.
9.Check coolant level. Add more if required.