Planning activities 3
.
._
.
.
. .
i
.
Table 2
Site planning activities
Activities
Wform
detailed site survey. Determine if building wire needs
/erification and gather preliminary customer data.
Hold
contract review meeting.
Prepare project plarl.
Hold customer meeting to discuss project plan and division of
responsibilities.
Hold Construction
Phase site survey to prioriiize site development
tasks.
.
Identify environmental, space, power and grounding requirements ant
prepare site accordingly.
Gather customer data.
Perform site inspections to ensure site is ready for installation.
Plan customer user training.
Note: In all the activities above, the Northern Telecom distributor is
generally responsible to ensure that these activities have been
implemented.
Installation planning 553-3001-l 20
.
.