Planning activities 5
Table 3
Milestone chart
I
Select the site.
Plan the equipment room layout.
Plan power and grounding, reserve and/or
battery requirements.
Plan cable requirements.
Plan and start renovations to implement
equipment room layout.
Continue site construction and renovation
tasks.
Install power, grounding, reserve power, air
conditioning, and heating.
Install special rigging such as overhead cable
racks and distribution frame equipment as
required.
3
Test site wiring to ensure minimum
requirements are met.
Complete construction and ensure power and
grounding are in place.
Test air conditioning and heating systems.
Complete final equipment room inspection
identifying and resolving any delivery
constraints.
Make equipment delivery arrangements.
Note: The Milestone chart shown is only an example of the activities
ecommended for site preparation. Depending on the complexity of the site, the
zhart will be more detailed with scheduled due dates (milestones) for each
33ivity group.
Installation planning 553-3001-120