Provisioning guidelines
Procedure 3-1
Provisioning guidelines
Note:
To determine the equipment requirements, follow the
provisioning guidelines in the order shown below. Worksheets and
Tables are all provided at the end of this document.
Step
1Define and forecast growth.
Step 2 Estimate ccs per terminal.
Step 3 Calculate number of trunks required.
Step 4 Calculate line, trunk, and console load.
Step
5Calculate DTP requirements.
Step 6 Calculate total system load.
Step 7 Calculate number of superloops required.
Step 8 Calculate number of Network groups required.
Step 9 Calculate number of PE cards required.
System engineering 553-3001-l 51