Step 1 Unpacking

Once the Epsilon STSTM UPS System has been inspected and received from the shipping courier, the unit should be moved with the use of a fork lift or pallet jack to a position as close to the final installation location as possible.

Prior to any installation, the following items should be observed upon receipt of the Epsilon STSTM 10-30 kVA UPS.

1.Inspect shipment for any damage prior to receipt. Damage claims should be filed directly with the courier. Replacements for damaged components should be ordered through MGE Customer Support Services at 1-800- 438-7373.

2.Remove wrapping and foam corners to verify that the equipment nameplate (located on the inside door of the cabinet) details a system that corresponds with the equipment ordered. See Figure QS-1.

3.The casters on the unit will allow it to be positioned into the final installation location. At this point, the leveling legs can be adjusted to provide a level and stable footing for the Epsilon STS™ system.

Figure QS-1Positioning of 200A Epsilon STS™.

LEVELING

CASTERS

JACKS

 

OPTIONAL SEISMIC

BRACKETS

SECURED USING 3/8 BOLT

QS —2