Epilson STSTM
1.The Source #2 SCR Switch #2 must be indicated closed on the display panel. If not, transfer the load to Source #2 by turning the Manual Control key switch on the front display panel to the “ON” position and pressing the Change Preferred Source Pushbutton. The STS should transfer to Source #2.
2.Open Source #1 isolation switch, CB1. (For
3.Lock Source #1 bypass switch, CB4, and remove the key.
4.Using the key(s), unlock and close Source #2 bypass switch, CB5. CB2, CB3A and CB3B (if installed) will shunt trip, isolating the static switch section.
Return to Normal Operation (load on Source #2)1.Close Source #2 isolation switch, CB2.
2.Wait for indication on the display panel that Source #2 SCR Switch #2 is closed.
3.Close Output isolation switch(es), CB3A and CB3B (if installed).
4.Open Source #2 bypass switch, CB5, and lock.
5.Close Source #1 isolation switch, CB1. (For
1.Bypass the load to Source #1 or #2 (see above procedures).
2.Close both source isolation switches, CB1 and CB2.
3.The static switch may now be tested without disturbing the load.
CAUTION: | EXPOSURE TO HAZARDOUS VOLTAGES. |
| Dangerous voltage levels are still present inside the |
| STS cabinet. When bypassed/isolated, control power |
| supply circuits are still live and power is provided for |
| indicator lights and emergency power off circuits. |
| Disconnect all sources of power before servicing. |
| Refer servicing to qualified service personnel. |
|
|
3 | Installation |