Epilson STSTM
Optional Steps
Should you require AC power on site prior to the arrival of the MGE Field Engineer, the following procedure will provide the AC power in the bypass mode. Should you have any questions about this procedure, do not hesitate to contact MGE Customer Support.
A.Ensure that all switches,
B.Apply input power to the source S1 input of the STS by closing the upstream circuit breaker for source S1. The STS controls will power up and issues alarm(s). Silence the alarm buzzer by pressing the “Alarm Silence” pushbutton on the front display panel.
C.Lock CB5 (S2 bypass switch) and remove the lock key (for
D.At this point, power will be available for site usage until the STS is properly commissioned.
E.Upon arrival of the MGE Field Service Engineer, the main power must be disconnected so that a safe and proper commissioning of the unit may be accomplished.
WARNING Do not, under any circumstance, close CB1, CB2, CB3A and
CB3B (if installed) until the unit has been commissioned by an
MGE Field Engineer.
Figure |
| Figure |
|
STS MONITOR |
|
|
|
|
| STS MONITOR |
|
|
| CB1 |
|
|
| CB4 |
|
CB1 | CB4 CB3A |
|
|
CB2 | CB5 CB3B |
| KEY INTERLOCKS |
| (2 - STANDARD | ||
|
| CB2 | |
|
| 4 - OPTIONAL) | |
|
|
| |
KEY INTERLOCKS |
| CB5 |
|
(2 - STANDARD |
|
|
|
4 - OPTIONAL) |
|
|
|
|
| CB3A |
|
|
| CB3B |
|
QS | Quick start |