5-39
Procedure in NEC ESMPRO Manager
Start
52. Select the target component in the [FTServer] tree.
53. Check the current state with the "Status" display on the target component screen.
54. Click the [Bring Up] button in the [Maintenance] screen for the target component.
A certain time is required for the start.
The start result can be confirmed by "State" on the target component screen. The result of
the start operation is reported by the NEC Express5800/ft series as an alert.
Stop
Perform the procedure below before replacing a component.
55. Select the target component in the [FTServer] tree.
56. Check the current state with the "State" display on the target component screen.
57. Click the [Bring Down] button in the [Maintenance] screen for the target component.
A certain time is required for the stop.
The stop result can be confirmed by "State" on the target component screen. The result of
the stop operation is reported by the NEC Express5800/ft series as an alert.
Sample screen of NEC ESMPRO Manager 1
[Maintenance] screen of PCI module
[PCI Module] – [Maintenance]