TOP VIEW

FRONT VIEW

Bracket from kit

Ground Wire

Ground Stud

Existing hinge

Nut from kit

Nut from kit

Front of

Front of 1085

Battery Cabinet

UPS

 

Figure 8. Attaching UPS Base to Series 1085 Base

12.Route the ground wire (from the field kit) from the customer ground stud in the battery cabinet, under the lower right-hand battery tray, through the access hole in the side panel of the UPS, and attach to customer ground stud in the UPS cabinet. Hardware is provided on each ground stud.

13.Repeat Steps 2 through 12 to attach additional Series 1085 Battery Cabinets to the other side of the first battery cabinet. Level the cabinets with the leveling screws.

14.Locate the cabinet connecting bracket from the field kit. Attach the bracket to the lower right-hand side of the Series 685 base using 2 M4 screws.

15.Locate the large flat bracket from the field kit. Place one end of the bracket over the stud on the bottom side of the UPS cabinet lower right-hand hinge, and the other end over the stud on the bottom side of the lower right-hand hinge on the Series 685 Battery Cabinet (see Figure 9).

16.Attach the bracket to the hinges with two M8 self-locking nuts from the field kit.

14

Powerware 9350 Series 685 and 1085 Auxiliary Battery Cabinets

 

Installation Manual 164201408 Rev. P00 053002

Page 20
Image 20
Powerware 685, 1085 installation manual TOP View Front View