Ground

Wire

Ground

Studs

Bracket from kit

Existing hinge

Front of

Nut from kit

Nut from kit

Front of

Battery Cabinet #1

 

Battery Cabinet #2

Figure 17. Connecting Two Series 1085 Bases

3.Locate the large flat bracket from the field kit. Place the bracket over the stud on the bottom side of battery cabinet #1 lower hinge, and over the stud on the bottom side of battery cabinet #1 lower hinge. Attach the bracket with two M8 self-locking nuts from the field kit (see Figure 17).

4.Locate the ground wire from the field kit. Route the ground wire from the customer ground stud in battery cabinet #1, under the lower right-hand battery tray, into the cable access area in battery cabinet #2, and attach to customer ground stud. Hardware is provided on each ground stud.

5.Repeat Steps 1 through 4 to join additional Series 1085 Battery Cabinets together.

24

Powerware 9350 Series 685 and 1085 Auxiliary Battery Cabinets

 

Installation Manual 164201408 Rev. P00 053002

Page 30
Image 30
Powerware 685 installation manual Connecting Two Series 1085 Bases