Verifying Operation of the Slide-rails and CMA
Use this procedure to ensure that the
Note – Two people are recommended for this procedure: one to move the server in and out of the rack, and one to observe the cables and CMA.
1.Slowly pull the server out of the rack until the
2.Inspect the attached cables for any binding or kinks.
3.Verify that the CMA extends fully from the
4.Push the server back into the rack, as described in the following
When the server is fully extended, you must release two sets of
a.The first set of stops are levers, located on the inside of each
The server will slide in approximately 18 inches (46 cm) and stop.
Verify that the cables and the CMA retract without binding before you continue.
b.The second set of stops are the
5.Adjust the cable straps and CMA as required.