Lift Arm Ball Joint Installation

Lift arm ball joints have been adjusted at the factory. The proper setting of left hand ball joint is 1.75 inch (45 mm) from end of lift arm to center of tapered stud (Fig. 28). The proper setting of right hand ball joint is 2.09 inch (53

mm)from end of lift arm to center of tapered stud (Fig. 29). These distances can be adjusted if deck alignment to traction unit is off or if the deck rubs against traction tires.

140 ft–lb (19 Kgm)

then continue tightening until slot in nut aligns with cotter pin hole

1.75 in. (45 mm)

1

Figure 28

1. Left ball joint

2.09 in. (53 mm)

1

140 ft–lb (19 Kgm)

then continue tightening until slot in nut aligns with cotter pin hole

Figure 29

1. Right ball joint

Contour 82 Cutting Unit

Page 10 – 18

Groundsmaster 3000/3000–D

Page 200