9 – Start-Up, Shutdown and Bypass (continued)

1

9-6 Shutdown Procedure (Single UPS) (continued)

4 Confirm that the UPS system is off and that all main output circuits

2are off. If the UPS system is connected to an external battery cabinet, turn off the external battery cabinet circuit breaker switch

A .

3

5 Switch off the output circuit breaker switch A . If the AC input

4power source is normal, the UPS system is ready for start-up.

Note: If the UPS system remains off for an extended period of time, it should be turned on periodically to allow the batteries to recharge. The UPS system should be turned on and the batteries should be recharged

5at least one uninterrupted 24-hour period every 3 months. Failure to recharge the batteries periodically may cause irreversible battery damage.

A

4

A

 

 

 

Output

Manual

Bypass

Main

5

Bypass

Input

Input

 

 

 

69-7 Preliminary Checklist (Parallel UPS)

Warning: Parallel redundancy requires exactly two UPS systems (1+1 redundancy). Do not attempt to link more than two UPS systems via parallel redundancy. The UPS systems must have the same rating and capacity for parallel redundancy installation. Attempting to link dissimilar UPS systems will damage the UPS systems and create a serious risk of personal injury and property damage.

7• All circuit breaker switches should be off, including the breakers of the external battery cabinets.

Confirm that no voltage potential exists between Neutral and Ground.

Confirm that the input power source matches the rating (voltage, frequency and phase) of the UPS systems.

You must use the control panel to set the parallel ID numbers of the UPS systems to be 1 and 2. See Section 10-11for information

8about setting the parallel ID numbers.

Note: After start-up, the UPS systems will perform a brief self-test and display the results on the LCD screen. After a successful self-test, the UPS systems will provide AC power to the connected equipment load.

99-8 Start-Up Procedure (Parallel UPS)

1 Connect the parallel redundancy cable A to the DB9 parallel redundancy port B of each UPS system.

10

11

2 If the UPS systems have external battery cabinets connected, switch on the external battery cabinet circuit breaker switch A of each battery pack.

12

13

 

B

B

A

1

 

A

2

14

28