VHX SERIES STEAMER - SERVICE PROCEDURES AND ADJUSTMENTS

c.Replace the orifice, pressure switch and connect the lead wires to the switch. Turn the power switch ON and adjust the pressure switch again as outlined in steps 4A and 4B. Verify the pilot gas valve is energizing.

d.If the pilot gas valve is not energizing and power is available to the pressure switch, turn the power switch OFF. Replace with a new air pressure switch and adjust the switch as outlined from step 3 thru the end of this procedure.

5.Restart the ignition sequence by "rapidly" turning the power switch OFF then back ON. A rapid switching is needed to keep the boiler from starting automatic blowdown.

A.Press the reset switch to start the ignition process.

1)Listen for gas pilot ignition to verify operation.

a.If gas pilot ignition is successful, turn the ON/OFF knob for the main gas valve back to ON.

b.Listen for main gas burner ignition to verify operation.

B.Verify the pilot and main burner both ignite in succession.

1)Restart the ignition sequence by "rapidly" turning the power switch OFF then back ON. A rapid switching is needed to keep the boiler from starting automatic blowdown.

2)Press the reset switch to start the ignition process.

C.Listen for main gas burner ignition to verify operation.

GAS PILOT PRESSURE

ADJUSTMENT

WARNING: DISCONNECT THE ELECTRICAL POWER TO THE MACHINE AT THE MAIN CIRCUIT BOX. PLACE A TAG ON THE CIRCUIT BOX INDICATING THE CIRCUIT IS BEING SERVICED.

WARNING: SHUT OFF THE GAS BEFORE SERVICING THE UNIT.

1.Open the cabinet base door to access pilot gas valve.

2.Remove the pilot pressure plug tap from the outlet side of valve.

A.Install a hose barb adaptor and attach a gas pressure manometer.

3.Turn the gas supply and power switch ON.

A.Once the boiler fills, press the reset switch to start the ignition process.

NOTE: The reset switch can be pressed after the green ready light on the switch comes ON. This indicates the water level in the boiler is at the minimum operating level.

F24700 (October 2001)

 

Page 34 of 68

 

Page 34
Image 34
Vulcan-Hart MHB24G, VHX24G5 manual GAS Pilot Pressure Adjustment