Sun Microsystems 96257 manual Planning and Implementation Overview, System Assurance Process Flow

Page 23

Planning and Implementation

1

Overview

 

This chapter provides an overview of key participants, timelines, and activities involved in planning for and implementing a VSM5 system.

Successful implementation requires regular communication and coordination between customer personnel and the Sun account team. This ongoing collaboration helps ensure that all factors critical to the implementation are identified and addressed before equip- ment is delivered to the site. The primary goals of the planning process are to:

Ensure the VSM5 system is properly designed to meet the requirements of the custom- er, and that it is ordered, delivered, installed, configured, tested, certified, and turned over with a minumum of disruptions and problems

Ensure the installation site infrastructure is equipped to handle the power, data-handling, and environmental requirements of VSM5 system equipment, and that customer person- nel are trained to assist with delivery, installation, configuration, testing, certification, and operation of the VSM5 system equipment.

Figure 1-1. System Assurance Process Flow

 

START

 

 

 

 

 

Proposal Acceptance

System Assurance

 

 

 

 

 

Planning Meetings

 

 

 

 

 

 

SA Team Corrects

 

 

 

Pre-installation

 

System Assurance

 

Checklists

 

Are the

 

 

 

 

Planning Meetings

 

 

 

 

 

Pre-Installation

NO

 

 

Checklists Complete

 

 

 

 

 

and Correct

 

 

 

 

Order Placement

?

 

 

 

 

YES

 

 

 

 

 

 

 

 

SSC or OM Contacts

 

 

 

 

 

SA Team for

 

Installation

 

 

 

More Information

 

 

 

 

NO

Are Order

 

 

 

 

Worksheets or Sales

 

 

 

 

 

Entry Forms Complete

Post installation

 

 

 

 

and Correct

 

 

 

 

Follow-up

 

 

 

 

?

 

 

 

 

 

 

 

 

 

YES

 

 

 

 

 

SSC or OM Approves

END

 

 

 

 

the Order and

 

 

 

 

Assigns a Ship Date

 

 

 

 

SSC = Shared Services Center

 

 

 

 

 

OM = Orders Management

 

 

 

 

 

SA = System Assurance

 

 

 

 

 

 

 

 

 

 

 

96257

Sun Confidential: Internal Only

1-23

 

Revision A

 

Image 23
Contents StorageTek Page Virtual Tape Storage Subsystem Vtss Revision a September Export Destination Control StatementDisclaimer of Warranties and Limitation of Liability Proprietary Information StatementSAP Revision History / Summary of ChangesContents Implementation Planning Site Readiness Planning 96257 Sun Confidential Internal Only Vii Revision a96257 Sun Confidential Internal Only Viii Revision a Figures Tables Cabling Notice Warranty NoticeClass 1 Laser Product Notice Electromagnetic Compatibility Product Safety StandardsHazardous Materials Handling Standards ConformancePage Definitions Internal Code License StatementSafety Precautions Safety / Fiber Optic / ESD PrecautionsStrictly Comply With Caution and Warning Messages Electrostatic Discharge PrecautionsProtect Your Eyes Fiber Optic Component Handling PrecautionsIntended Audience Optimizing Content For Electronic ViewingAbout This Guide Product OverviewExamples Description of Convention Alert MessagesNotational and Typographic Conventions Reference Documents Where to Find Additional InformationVSM Engineering Website SE Support Tools ColophonSystem Assurance Process Flow Planning and Implementation OverviewCreating Planning Teams Planning / Readiness / Implementation Timelines Page Key High-Level Activities Key Sub-Tasks Key Participants Configuration PlanningConfiguration Planning Overview VSM Quick Tool Tool Selection Screen Defining Customer RequirementsVSM Sizer Tool VSM Sizer ToolMVC Sizer Tool MVC Sizer ToolMVC Migration Tool MVC Migration ToolCDS Sizer Tool CDS Sizer ToolVSM5-VTSS Environmental Requirements Vtss Configuration PlanningVSM5-VTSS Physical Characteristics VSM5-VTSS Physical CharacteristicsVSM5-VTSS Model Numbers / Configurations / Capacities Model Numbers / Configurations / CapacitiesAdditional Prerequisites for Ficon RTDs Prerequisites for Ficon ConnectivityNative Ficon Attachment Options Native Ficon AttachmentSingle-Mode vs. Multi-Mode Ficon Cabling Ficon Data Transfer RatesFicon Cabling Short-Wave vs. Long-Wave Connections Ficon Channel Card Configuration 4 VCF Cards VCF3 Ficon Card Configuration ExamplesFicon Channel Card Configuration 6 VCF Cards Description / Length Part Number Fibre Channel Cables Available LengthsFibre Channel Cables Available Lengths VSM5-VTSS DC Power Supply Voltage Ripple AC Source Power Specifications and ConnectorsDC Power Supply Voltage Ripple Specifications VSM5-VTSS AC Source Power Specifications and ConnectorsPower Requirements Implementation Planning Overview Implementation PlanningPage Site Readiness Planning Overview Site Readiness PlanningSite Evaluation Internal Considerations Site Evaluation External ConsiderationsTransfering Equipment Point-to-Point Structural Dimensions and ObstructionsEmergency Power Control Data Center SafetySite Electrical Power Distribution System Site Power Distribution SystemsSource Power Voltage Range Frequency Range Hz Source Power Requirements for VSM5 EquipmentHvac Requirements Electrostatic DischargeFloor Loading Requirements Environmental Requirements and HazardsFloor Construction Requirements VSM5-VTSS Cabinet Superimposed Floor Loading Example VSM5-VTSS Floor Loading SpecificationsSite Evaluation Internal Considerations Raised Flooring Horizontal Force Chart VSM5-VTSS Cabinet Weight Distribution and Leveler LocationsPhysical Space Requirements VSM5-VTSS Cabinet Dimensions for Physical Space PlanningPage Specifications and Additional Information Motherboard and FRU Interconnections Side Motherboard and FRU Interconnections Side Figure A-3. VSM5-VTSS Power Safety Grounding Diagram Side Power Safety Grounding Diagram SideFigure A-4. VSM5-VTSS Power Safety Grounding Diagram Side Figure A-5. VSM5-VTSS Power System Diagram Power System DiagramFigure A-6. VSM5-VTSS Data Paths and Interfaces Data Paths and InterfacesTable A-2. VShell Command Reference Fiber Optic Cable SpecificationsVShell Command Reference Table A-1. Fiber Optic Cable SpecificationsFigure A-7. Sample Iocp Gen for Ficon Configuration Sample Iocp Gen for Ficon ConfigurationSequential Device Parameters Numbers Virtual Tape Drive Mapping and Host AddressingTable A-4. VSM5-VTSS FRU Identifiers FRU IdentifiersISP1 Hex Decimal Unit.Tray.Slot Logic Motherboard and CardsPhysical Array Disk Drive Tray Hex Decimal Unit.Tray.Slot Logic Power Supply FansCard Cage Impellers Hex Decimal Unit.Tray.Slot Physical Array Disk Drive Tray DA.5.DRV0 Figure A-8. Array Drive Module States and Relationships Array Drive Module Status DescriptionsUnavailable Partition Table A-5. Array Drive Module Status DescriptionsMedia Acceptance Test MAT Partition Spares PartitionPage Ficon Channel Extension Guidelines Definition of Terms Understand Channel Extension Performance Limitations General Channel Extension ConsiderationsFicon Topologies Placement of Extension EquipmentInteroperability Testing Host Ficon Channel Extension Sample ConfigurationsChannel Director/Switch Extender Tape SiloFigure B-4. VTSS-to-RTD Channel Extension Direct Attachment McData/CNT Channel Extension Interoperability McData/CNT Channel Extension InteroperabilityISL Failover Is Supported Only in Shuttle Mode Cisco Systems Channel Extension Interoperability Page Glossary Sun Confidential Internal Only 96257 Revision a 96257 Sun Confidential Internal Only Revision a Data compression. See compression 96257 Sun Confidential Internal Only Revision a Sun Confidential Internal Only 96257 Revision a Functional device. See functional volume Technology with ISO 96257 Sun Confidential Internal Only Revision a MLC. Machine-Level Control Part number Service Delivery Platform SDP. a Sun StorageTek 96257 Sun Confidential Internal Only Revision a Sun Confidential Internal Only 96257 Revision a Forms and Reference Notes Host System Configuration Information Customer Personnel Contacts Sun StorageTek / QSP Personnel Contacts Planning Worksheet 1 Planning Worksheet 2 Planning Worksheet 3 Planning Worksheet 4 Planning Worksheet 5 Software Information Hardware Information Tape Devices Hardware Information Switches / Routers Hardware Information SDP and Modem Devices Account Account Account Account Account Page Headquarters