Sun Microsystems 96257 manual Site Readiness Planning Overview

Page 45

Site Readiness Planning

4

 

 

This chapter provides information about activities designed to ensure the site is equipped to accommodate the power, safety, environmental, HVAC, and data handling requirements of VSM5 system equipment.

Table 4-1.Site Readiness Planning Overview

Key High-Level Activities

Key Sub-Tasks

Key Participants

• Select site readiness team members,

• Verify site power, safety, environmen-

 

and define roles and responsibilities.

tal, HVAC, and data handling capabili-

 

• Complete site surveys to:

ties match VSM5-VTSS requirements.

 

- Document existing or potential exter-

• Define plan to eliminate/mitigate envi-

 

nal and internal environmental haz-

ronmental hazards.

 

ards

• Evaluate floor load ratings along transit

 

- Assess site power, safety, environ-

path and at the VSM5-VTSS installa-

Customer: site engineer; fa-

mental, HVAC, and data handling ca-

tion location.

cilities manager; data center

pabilities versus VSM5 system re-

• Verify site door, hall and ceiling clear-

manager; network adminis-

quirements

ances, elevator capacity, ramp angles,

trator

- Confirm floor load ratings along the

etc. match VSM5-VTSS requirements.

Sun: technical support spe-

transit path and at the installation lo-

• Identify required infrastructure modifi-

cialist; systems engineer

cation for VSM5-VTSS cabinets

cations/upgrades; set work completion

 

- Assess ceiling, hallway, and door

schedule.

 

clearances, elevator capacities, and

• Evaluate readiness progress, and certi-

 

ramp angles versus VSM5-VTSS

fy site readiness.

 

cabinet requirements.

• Complete applicable Appendix D work-

 

• Attend planning meetings.

sheets.

 

Key site readiness planning considerations include, but are not limited to:

Site surveys to evaluate and eliminate or mitigate factors which could negatively affect delivery, installation, and operation of VSM5 system equipment.

A plan for the layout and location of VSM5 system equipment and cabling that allows for efficient use and easy maintenance, plus adequate space and facilities for Sun support personnel and their equipment.

Facilities construction that provides an optimum operating environment for VSM5 sys- tem equipment and personnel, as well as safe flooring and protection from fire, flooding, contamination, and other potential hazards.

Scheduling of key events and task completion dates for facilities upgrades, personnel training, and delivery, implementation, installation, testing, and certification activities.

Customers ultimately are responsible for ensuring that their site is physically prepared to receive and operate VSM5 system equipment, and that the site meets the minimum spec- ifications for equipment operation as detailed in this guide.

96257

Sun Confidential: Internal Only

4-45

 

Revision A

 

Image 45
Contents StorageTek Page Virtual Tape Storage Subsystem Vtss Disclaimer of Warranties and Limitation of Liability Export Destination Control StatementProprietary Information Statement Revision a SeptemberSAP Revision History / Summary of ChangesContents Implementation Planning Site Readiness Planning 96257 Sun Confidential Internal Only Vii Revision a96257 Sun Confidential Internal Only Viii Revision a Figures Tables Warranty Notice Class 1 Laser Product NoticeCabling Notice Hazardous Materials Handling Product Safety StandardsStandards Conformance Electromagnetic CompatibilityPage Definitions Internal Code License StatementSafety Precautions Safety / Fiber Optic / ESD PrecautionsStrictly Comply With Caution and Warning Messages Electrostatic Discharge PrecautionsProtect Your Eyes Fiber Optic Component Handling PrecautionsAbout This Guide Optimizing Content For Electronic ViewingProduct Overview Intended AudienceAlert Messages Notational and Typographic ConventionsExamples Description of Convention Reference Documents Where to Find Additional InformationVSM Engineering Website SE Support Tools ColophonSystem Assurance Process Flow Planning and Implementation OverviewCreating Planning Teams Planning / Readiness / Implementation Timelines Page Configuration Planning Configuration Planning OverviewKey High-Level Activities Key Sub-Tasks Key Participants VSM Quick Tool Tool Selection Screen Defining Customer RequirementsVSM Sizer Tool VSM Sizer ToolMVC Sizer Tool MVC Sizer ToolMVC Migration Tool MVC Migration ToolCDS Sizer Tool CDS Sizer ToolVSM5-VTSS Physical Characteristics Vtss Configuration PlanningVSM5-VTSS Physical Characteristics VSM5-VTSS Environmental RequirementsVSM5-VTSS Model Numbers / Configurations / Capacities Model Numbers / Configurations / CapacitiesAdditional Prerequisites for Ficon RTDs Prerequisites for Ficon ConnectivityNative Ficon Attachment Options Native Ficon AttachmentFicon Data Transfer Rates Ficon Cabling Short-Wave vs. Long-Wave ConnectionsSingle-Mode vs. Multi-Mode Ficon Cabling Ficon Channel Card Configuration 4 VCF Cards VCF3 Ficon Card Configuration ExamplesFicon Channel Card Configuration 6 VCF Cards Fibre Channel Cables Available Lengths Fibre Channel Cables Available LengthsDescription / Length Part Number DC Power Supply Voltage Ripple Specifications AC Source Power Specifications and ConnectorsVSM5-VTSS AC Source Power Specifications and Connectors VSM5-VTSS DC Power Supply Voltage RipplePower Requirements Implementation Planning Overview Implementation PlanningPage Site Readiness Planning Overview Site Readiness PlanningSite Evaluation Internal Considerations Site Evaluation External ConsiderationsTransfering Equipment Point-to-Point Structural Dimensions and ObstructionsEmergency Power Control Data Center SafetySite Electrical Power Distribution System Site Power Distribution SystemsSource Power Voltage Range Frequency Range Hz Source Power Requirements for VSM5 EquipmentHvac Requirements Electrostatic DischargeEnvironmental Requirements and Hazards Floor Construction RequirementsFloor Loading Requirements VSM5-VTSS Floor Loading Specifications Site Evaluation Internal ConsiderationsVSM5-VTSS Cabinet Superimposed Floor Loading Example Raised Flooring Horizontal Force Chart VSM5-VTSS Cabinet Weight Distribution and Leveler LocationsPhysical Space Requirements VSM5-VTSS Cabinet Dimensions for Physical Space PlanningPage Specifications and Additional Information Motherboard and FRU Interconnections Side Motherboard and FRU Interconnections Side Figure A-3. VSM5-VTSS Power Safety Grounding Diagram Side Power Safety Grounding Diagram SideFigure A-4. VSM5-VTSS Power Safety Grounding Diagram Side Figure A-5. VSM5-VTSS Power System Diagram Power System DiagramFigure A-6. VSM5-VTSS Data Paths and Interfaces Data Paths and InterfacesVShell Command Reference Fiber Optic Cable SpecificationsTable A-1. Fiber Optic Cable Specifications Table A-2. VShell Command ReferenceFigure A-7. Sample Iocp Gen for Ficon Configuration Sample Iocp Gen for Ficon ConfigurationSequential Device Parameters Numbers Virtual Tape Drive Mapping and Host AddressingTable A-4. VSM5-VTSS FRU Identifiers FRU IdentifiersISP1 Hex Decimal Unit.Tray.Slot Logic Motherboard and CardsHex Decimal Unit.Tray.Slot Logic Power Supply Fans Card Cage ImpellersPhysical Array Disk Drive Tray Hex Decimal Unit.Tray.Slot Physical Array Disk Drive Tray DA.5.DRV0 Figure A-8. Array Drive Module States and Relationships Array Drive Module Status DescriptionsMedia Acceptance Test MAT Partition Table A-5. Array Drive Module Status DescriptionsSpares Partition Unavailable PartitionPage Ficon Channel Extension Guidelines Definition of Terms Understand Channel Extension Performance Limitations General Channel Extension ConsiderationsPlacement of Extension Equipment Interoperability TestingFicon Topologies Channel Director/Switch Extender Ficon Channel Extension Sample ConfigurationsTape Silo HostFigure B-4. VTSS-to-RTD Channel Extension Direct Attachment McData/CNT Channel Extension Interoperability McData/CNT Channel Extension InteroperabilityISL Failover Is Supported Only in Shuttle Mode Cisco Systems Channel Extension Interoperability Page Glossary Sun Confidential Internal Only 96257 Revision a 96257 Sun Confidential Internal Only Revision a Data compression. See compression 96257 Sun Confidential Internal Only Revision a Sun Confidential Internal Only 96257 Revision a Functional device. See functional volume Technology with ISO 96257 Sun Confidential Internal Only Revision a MLC. Machine-Level Control Part number Service Delivery Platform SDP. a Sun StorageTek 96257 Sun Confidential Internal Only Revision a Sun Confidential Internal Only 96257 Revision a Forms and Reference Notes Host System Configuration Information Customer Personnel Contacts Sun StorageTek / QSP Personnel Contacts Planning Worksheet 1 Planning Worksheet 2 Planning Worksheet 3 Planning Worksheet 4 Planning Worksheet 5 Software Information Hardware Information Tape Devices Hardware Information Switches / Routers Hardware Information SDP and Modem Devices Account Account Account Account Account Page Headquarters