Planning and Implementation Overview

The dock manager and/or facilities manager and Sun customer service manager identify any special shipping requirements, and notify the Sun manufacturing group as needed.

The Sun sales representative completes and submits the equipment sales order, in- cluding all necessary cabling and spare parts.

The network administrator and data center manager select appropriate personnel for VSM5 system training, targeting completion for no later than one week before deliv- ery of equipment.

3.One month before the scheduled delivery date for the VSM5 system equipment:

The network administrator, data center manager, and Sun sales representative verify that all required components in the specified configuration, and all cables of the re- quired length, have been ordered.

The Sun customer service manager reconfirms the scheduled system delivery date with the Sun manufacturing facility.

The facilities manager verifies compliance of input power systems and power cabling in the data center. See “Site Power Distribution Systems” on page 4-49.

The facilities manager verifies environmental compliance and HVAC systems readi- ness in the delivery, staging, and installation areas.

The site engineer and structural engineer verify floor loading compliance along the delivery path and at the data center installation location. See “Floor Construction Re- quirements” and “Floor Loading Requirements” on page 4-52.

The Sun customer services manager identifies which Sun personnel will perform the VSM5 system installation at the customer site.

4.Two weeks before the scheduled delivery date for the VSM5 system equipment:

The Sun sales representative verifies that all parts and bills of material (BOM) have been delivered to the site to allow hardware and software conversions and feature changes in previously-installed equipment.

The facilities manager and Sun customer service manager verify the delivery dock and data center personnel, and Sun CSEs who will be available to accept delivery of the system equipment, and assist in unpackaging, point-to-point transfer, and instal- lation of system equipment.

The facilities manager, data center manager, and Sun customer service manager agree on firm dates and timeframes for delivery, installation, certification, and opera- tional testing of system equipment.

1-26

Sun Confidential: Internal Only

96257

 

Revision A

 

Image 26
Contents StorageTek Page Virtual Tape Storage Subsystem Vtss Proprietary Information Statement Export Destination Control StatementDisclaimer of Warranties and Limitation of Liability Revision a SeptemberRevision History / Summary of Changes SAPContents 96257 Sun Confidential Internal Only Vii Revision a Implementation Planning Site Readiness Planning96257 Sun Confidential Internal Only Viii Revision a Figures Tables Cabling Notice Warranty NoticeClass 1 Laser Product Notice Standards Conformance Product Safety StandardsHazardous Materials Handling Electromagnetic CompatibilityPage Internal Code License Statement DefinitionsSafety / Fiber Optic / ESD Precautions Safety PrecautionsElectrostatic Discharge Precautions Strictly Comply With Caution and Warning MessagesFiber Optic Component Handling Precautions Protect Your EyesProduct Overview Optimizing Content For Electronic ViewingAbout This Guide Intended AudienceExamples Description of Convention Alert MessagesNotational and Typographic Conventions Where to Find Additional Information Reference DocumentsVSM Engineering Website Colophon SE Support ToolsPlanning and Implementation Overview System Assurance Process FlowCreating Planning Teams Planning / Readiness / Implementation Timelines Page Key High-Level Activities Key Sub-Tasks Key Participants Configuration PlanningConfiguration Planning Overview Defining Customer Requirements VSM Quick Tool Tool Selection ScreenVSM Sizer Tool VSM Sizer ToolMVC Sizer Tool MVC Sizer ToolMVC Migration Tool MVC Migration ToolCDS Sizer Tool CDS Sizer ToolVSM5-VTSS Physical Characteristics Vtss Configuration PlanningVSM5-VTSS Physical Characteristics VSM5-VTSS Environmental RequirementsModel Numbers / Configurations / Capacities VSM5-VTSS Model Numbers / Configurations / CapacitiesPrerequisites for Ficon Connectivity Additional Prerequisites for Ficon RTDsNative Ficon Attachment Native Ficon Attachment OptionsSingle-Mode vs. Multi-Mode Ficon Cabling Ficon Data Transfer RatesFicon Cabling Short-Wave vs. Long-Wave Connections VCF3 Ficon Card Configuration Examples Ficon Channel Card Configuration 4 VCF CardsFicon Channel Card Configuration 6 VCF Cards Description / Length Part Number Fibre Channel Cables Available LengthsFibre Channel Cables Available Lengths VSM5-VTSS AC Source Power Specifications and Connectors AC Source Power Specifications and ConnectorsDC Power Supply Voltage Ripple Specifications VSM5-VTSS DC Power Supply Voltage RipplePower Requirements Implementation Planning Implementation Planning OverviewPage Site Readiness Planning Site Readiness Planning OverviewSite Evaluation External Considerations Site Evaluation Internal ConsiderationsStructural Dimensions and Obstructions Transfering Equipment Point-to-PointData Center Safety Emergency Power ControlSite Power Distribution Systems Site Electrical Power Distribution SystemSource Power Requirements for VSM5 Equipment Source Power Voltage Range Frequency Range HzElectrostatic Discharge Hvac RequirementsFloor Loading Requirements Environmental Requirements and HazardsFloor Construction Requirements VSM5-VTSS Cabinet Superimposed Floor Loading Example VSM5-VTSS Floor Loading SpecificationsSite Evaluation Internal Considerations VSM5-VTSS Cabinet Weight Distribution and Leveler Locations Raised Flooring Horizontal Force ChartVSM5-VTSS Cabinet Dimensions for Physical Space Planning Physical Space RequirementsPage Specifications and Additional Information Motherboard and FRU Interconnections Side Motherboard and FRU Interconnections Side Power Safety Grounding Diagram Side Figure A-3. VSM5-VTSS Power Safety Grounding Diagram SideFigure A-4. VSM5-VTSS Power Safety Grounding Diagram Side Power System Diagram Figure A-5. VSM5-VTSS Power System DiagramData Paths and Interfaces Figure A-6. VSM5-VTSS Data Paths and InterfacesTable A-1. Fiber Optic Cable Specifications Fiber Optic Cable SpecificationsVShell Command Reference Table A-2. VShell Command ReferenceSample Iocp Gen for Ficon Configuration Figure A-7. Sample Iocp Gen for Ficon ConfigurationVirtual Tape Drive Mapping and Host Addressing Sequential Device Parameters NumbersFRU Identifiers Table A-4. VSM5-VTSS FRU IdentifiersHex Decimal Unit.Tray.Slot Logic Motherboard and Cards ISP1Physical Array Disk Drive Tray Hex Decimal Unit.Tray.Slot Logic Power Supply FansCard Cage Impellers Hex Decimal Unit.Tray.Slot Physical Array Disk Drive Tray DA.5.DRV0 Array Drive Module Status Descriptions Figure A-8. Array Drive Module States and RelationshipsSpares Partition Table A-5. Array Drive Module Status DescriptionsMedia Acceptance Test MAT Partition Unavailable PartitionPage Ficon Channel Extension Guidelines Definition of Terms General Channel Extension Considerations Understand Channel Extension Performance LimitationsFicon Topologies Placement of Extension EquipmentInteroperability Testing Tape Silo Ficon Channel Extension Sample ConfigurationsChannel Director/Switch Extender HostFigure B-4. VTSS-to-RTD Channel Extension Direct Attachment McData/CNT Channel Extension Interoperability McData/CNT Channel Extension InteroperabilityISL Failover Is Supported Only in Shuttle Mode Cisco Systems Channel Extension Interoperability Page Glossary Sun Confidential Internal Only 96257 Revision a 96257 Sun Confidential Internal Only Revision a Data compression. See compression 96257 Sun Confidential Internal Only Revision a Sun Confidential Internal Only 96257 Revision a Functional device. See functional volume Technology with ISO 96257 Sun Confidential Internal Only Revision a MLC. Machine-Level Control Part number Service Delivery Platform SDP. a Sun StorageTek 96257 Sun Confidential Internal Only Revision a Sun Confidential Internal Only 96257 Revision a Forms and Reference Notes Host System Configuration Information Customer Personnel Contacts Sun StorageTek / QSP Personnel Contacts Planning Worksheet 1 Planning Worksheet 2 Planning Worksheet 3 Planning Worksheet 4 Planning Worksheet 5 Software Information Hardware Information Tape Devices Hardware Information Switches / Routers Hardware Information SDP and Modem Devices Account Account Account Account Account Page Headquarters