Briggs & Stratton 01929-1, 01928-1 manual System Operation, Testing the Automatic Transfer Switch

Page 10

Briggs & Stratton Power Products Automatic Transfer Switch

Installation and Operator’s Manual

SYSTEM OPERATION

To select automatic transfer operation, do the following:

1A. For models 01813-1 & 01814-1, set service disconnect switch that sends utility power to transfer switch contactor to “On” position.

B.For models 01928-1 & 01929-1, set service disconnect switch that sends utility power to transfer switch utility disconnect circuit breaker to “On” position.

2.For models 01928-1 & 01929-1, set transfer switch utility disconnect circuit breaker to “On” position.

3.Set generator’s main circuit breaker to its “On” position.

4.Install 15 Amp fuse in control panel on generator.

5A. If generator is equipped with a system ON/OFF switch, set switch to “On” position.

B.If generator is equipped with a AUTO/OFF/MANUAL switch, set switch to “AUTO” position.

The system will now be in automatic operation mode.

TESTING THE AUTOMATIC TRANSFER SWITCH

Turn the service disconnect feeding the transfer switch, to the “Off” position.The automatic sequence will follow.To go back to utility power, turn the service disconnect to the “On” position.

Automatic Sequence

Utility Fail

The Home Standby Generator set senses when utility voltage is below 70 percent of nominal. Engine start sequence is initiated after 6 second time delay.

Engine Warm-Up

Time delay to allow for engine warm-up before transfer fixed at 20 seconds or 50 seconds with removal of jumper on control board.

Transfer

Transfer from utility to standby supply occurs after standby voltage is above set levels. Minimum engine run time is

5 minutes after transfer.

Utility Pickup

Voltage pickup level is 80 percent of nominal voltage.

Retransfer

Retransfer from standby to utility supply is approximately 10 seconds after utility voltage supply is above pickup level and minimum run time is completed.

Engine Cool Down

Engine will run for 60 seconds after retransfer.

When Calling the Factory

Before contacting Briggs and Stratton Power Products regarding service or repair of this transfer switch, obtain the Model Number and Serial Number from the unit data decal located on or inside the case.

To contact Briggs and Stratton Power Products call 1-800-743-4115, between 8:00 AM and 5:00 PM CT.

10

Image 10
Contents Amp / 200 Amp Table of Contents Only qualified electricians should attempt installation Important Safety InstructionsUse transfer switch only for intended uses Introduction For the Home OwnerOwner Orientation Shipment Contents InstallationDelivery Inspection Typical Transfer Switch Mounting for Models 01928-1 Power Wiring Interconnections Typical Installation Diagram for Transfer Switch Testing the Automatic Transfer Switch System OperationUL 1008 Listed Transfer Switch Model SpecificationsFault Current Rating ,000 RMS Symmetrical Amperes Troubleshooting Problem Cause CorrectionInstallation and Operator’s Manual Transfer Switch Schematic Models 01813-1Transfer Switch Wiring Diagram Models 01928-1Description Transfer Switch Exploded View & Parts ListItems without part numbers are common fasteners DECAL, 200A,ATS LOCKWASHER, #10 BUS BAR Installation and Operator’s Manual Limited Warranty Guide dinstallation et dutilisation Table DES MatièresAvertissement Introduction Au Détaillant ou à lEntrepreneur Procédant à lInstallationAu Propriétaire Résidentiel Conseils au Propriétaire Responsabilités de lInstallateurDescription de lÉquipement Déballage InstallationConsignes dinstallation Vérification de la LivraisonUne installation alternative du commutateur de transfert Interconnexions du Câblage dAlimentation Câblage de contrôleSchéma dInstallation Typique du Commutateur de Transfert Séquence Automatique FonctionnementMise À Lessai DU Commutateur DE Transfert Automatique Si vous Devez Communiquer avec lUsineCharge maximum/circuit CaractéristiquesUL 1008 Enuméré Commutateur de Transfert Modéle Valeur nominale desDépannage Garantie Limitée Tabla DE Contenido Manual de Instalación y del OperarioAdvertencia PrecauciónIntroducción Para el Propietario DomésticoDescripción del Equipo Orientación para el PropietarioResponsabilidades del Instalador Lea y cumpla las instrucciones incluidas en el manualPautas de Montaje InstalaciónDesempaque Inspección al Momento de la EntregaFigura 13 Montaje de un Conectador Alternativo Cableado de Control de Supervisión Interconexiones de Cableado de EnergíaContactor del Acondicionador de aire Alimentación Neutro Figura 11 Un Esquema Típico de Instalación para Conectador Secuencia Automática Sistema FuncionamientoPrueba DEL Conectador Automático Si Necesita Llamar a FábricaEspecificaciones Problemo Causa AccionReparacion DE Averias Garantía Limitada