MGE UPS Systems 40-150kVA user manual AC Output, Battery

Page 30

Installation and User Manual

2.6.4AC Output

The connections to be made are the three phases, and ground cables from the load source to the UPS. The output cables are terminated at the Output Terminal Block (TB2) for 40-80kVA, and the output busbars for 100- 150kVA.

Load cables must be run separately from all other cables (power supply or computer-system interconnection cables). They should not pass near interference-emitting equipment or sensitive loads.

2.6.5Battery

The connections to be made are the positive, negative, and ground cables from the battery cabinet to the UPS. These are terminated at the appropriate connections in the UPS cabinet (see Figures 2-3 and 2-4). Additionally, control wires and temperature sensors in the battery cabinet must be terminated. Refer to the battery cabinet installation drawings for more details.

Figure 2-3: Connections for Comet 40-80kVA UPS.

Separate Bypass

 

 

 

 

 

 

 

Main Input

 

 

 

Output

Fan Control

 

 

 

 

Fan and

 

Input Terminal

 

Battery

Terminal Block

Terminal Block

Switch

 

 

Teleservice Fuses

 

Block TB3

Connections

 

 

TB1

 

 

 

TB2

 

SR2

 

 

 

FU7-FU12

 

(Optional)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Ground Busbar

Neutral Busbar

Figure 2-4: Connections for Comet 100-150kVA UPS.

OUTPUT

B4

A4

OPT

A5

BYPASS

B3

A3

C4

C5 B5

+

C3

-

INPUT

BATT.

86-160310-00 E00

Installation

2 — 5

Image 30
Contents Comet 40-150kVA Page Comet Revision HistoryImportant Safety Instructions Comet 40-150kVAProduct Safety Certification Standards Three Phase UPSSafety of Persons Special PrecautionsThis page left blank intentionally Contents Maintenance OperationCustomer Care Center Three Phase Products MGE Warranty & Proprietary Rights for Three Phase ProductsWarranty and Product Registration TablesUPS Serial Number Battery Serial Number This page left blank intentionally 86-160310-00 E00 Comet 40-150kVA Symbol Usage Section DescriptionsSystem Description and Specifications ScopeGeneral Description Single Line Diagram for the Comet 40-80kVA Major Components Detail Behind Item Rear View of the Comet 40-80kVA FU1-FU21 Control Fuses TOP Conduit Landing for Cable Access to Pcas Specifications Power factor PhasesWires DC Ratings Battery voltage 25 CHumidity Environmental Specifications Temperature6 DB15 Connector Pinouts and Designations AltitudeOptions and Accessories Chaptername This page left blank intentionally Handling InstallationReceiving For assistanceMay adversely affect life Prerequisite to InstallationStorage EnvironmentalMechanical Short circuit when the unit is working on Static SwitchProper trip settings ElectricalInstallation Procedures ConnectionsBattery AC OutputChaptername This page left blank intentionally Power Flow, For On Battery Operation Power FlowPower Flow, For Normal Operation OperationGraphical User Interface, Controls and Indicators Power Flow, For Bypass OperationComet Front Panel GUI, Controls and Indicators Battery Status LED Emergency Power OffFault LED Fault ResetStartup Procedures Inverter Manual StartupPreliminary Checks Battery Duration Operating ProceduresOperation on Battery Power Return to AC PowerOutput Current Overload Curve Emergency Shutdown Using EPO/REPO Maintenance BypassForced Transfer Move the fan control switch SR2 to the OFF position Powering Down Shutdown ProceduresAlarms Inverter ShutdownMaintenance Battery SafetyPreventive Maintenance Replacement Parts Level DescriptionApplicable within the United States, Canada and Mexico Warranty Extension Warranty+ User InformationProduct Information Scheduling Field Service Engineer Support MGE Customer Care Center Three Phase ProductsTechnical Support and Product Services Return Policy for Repair of Three Phase Products RGAComet 40-150kVA Glossary Term used Definition / MeaningFCC NEC This page left blank intentionally Reorder Form Scenic Avenue Costa Mesa, CA Page Page Contact MGE