MGE UPS Systems 40-150kVA user manual Move the fan control switch SR2 to the OFF position

Page 41

Installation and User Manual

NOTE

The cooling fans will remain operational when the UPS is placed on

 

Maintenance Bypass mode to prevent the optional input/output transformers

 

inside the UPS from overheating. If it is necessary to de-energize the fans,

 

move the fan control switch (SR2) to the “OFF” position.

 

 

 

 

CAUTION

In this mode of operation, the UPS is ready for maintenance, but voltage is

 

still present on terminal blocks and various internal components.

 

 

Now the UPS is ready for maintenance.

3.8.2From Maintenance Bypass to Normal Mode

WARNING

Failure to follow the proper Startup sequence will result in load loss. After

 

SR1 is set to “TRANSFER,” it takes the UPS five (5) to six (6) \seconds to test

 

the input power before turning on the “Static Switch”. During this time, the

 

load is still supplied by the Maintenance Bypass line, and moving SR1 to

 

“NORMAL” will result in interruption of power to the load.

 

 

 

1.Move the fan control switch (SR2) to the “ON” position if the cooling fans were de-energized during maintenance.

2.Turn the manual bypass switch SR1 to the "TRANSFER" position.

3.Wait for the GUI display to go on (at least 5 seconds).

4.Turn the Inverter off by pressing the gray "Inverter OFF" pushbutton on the front panel for approximately 3 seconds if your Comet has been programmed to automatically restart.

CAUTION

ALWAYS turn the Inverter off before rotating the Manual Bypass Switch (SR1).

5.Close the battery disconnect circuit breaker(s) QF1.

6.Turn the manual bypass switch SR1 to the "NORMAL" position.

7.Turn the Inverter on by pressing the green “Inverter ON" pushbutton on the front panel. If the transfer conditions are not satisfied (bypass out of tolerance or other reason), a forced transfer will be required. Refer to the "Forced Transfers" section for more information.

Now the UPS is in normal operating mode. The green "Load Protected" LED is illuminated on the front panel, and the operating status of the UPS is provided by the GUI display.

86-160310-00 E00

Operation

3 —9

Image 41
Contents Comet 40-150kVA Page Revision History CometComet 40-150kVA Important Safety InstructionsSafety of Persons Certification Standards Three Phase UPSProduct Safety Special PrecautionsThis page left blank intentionally Contents Operation MaintenanceWarranty and Product Registration MGE Warranty & Proprietary Rights for Three Phase ProductsCustomer Care Center Three Phase Products TablesUPS Serial Number Battery Serial Number This page left blank intentionally 86-160310-00 E00 Section Descriptions Comet 40-150kVA Symbol UsageGeneral Description System Description and SpecificationsScope Single Line Diagram for the Comet 40-80kVA Major Components Detail Behind Item Rear View of the Comet 40-80kVA FU1-FU21 Control Fuses TOP Conduit Landing for Cable Access to Pcas Specifications Wires PhasesPower factor DC Ratings Battery voltage 25 C6 DB15 Connector Pinouts and Designations Environmental Specifications TemperatureHumidity AltitudeOptions and Accessories Chaptername This page left blank intentionally Receiving InstallationHandling For assistanceStorage Prerequisite to InstallationMay adversely affect life EnvironmentalProper trip settings Short circuit when the unit is working on Static SwitchMechanical ElectricalConnections Installation ProceduresAC Output BatteryChaptername This page left blank intentionally Power Flow, For Normal Operation Power FlowPower Flow, For On Battery Operation OperationPower Flow, For Bypass Operation Graphical User Interface, Controls and IndicatorsComet Front Panel GUI, Controls and Indicators Fault LED Emergency Power OffBattery Status LED Fault ResetPreliminary Checks Startup ProceduresInverter Manual Startup Operation on Battery Power Operating ProceduresBattery Duration Return to AC PowerOutput Current Overload Curve Forced Transfer Emergency Shutdown Using EPO/REPOMaintenance Bypass Move the fan control switch SR2 to the OFF position Alarms Shutdown ProceduresPowering Down Inverter ShutdownPreventive Maintenance MaintenanceBattery Safety Level Description Replacement PartsApplicable within the United States, Canada and Mexico Product Information Warranty Extension Warranty+User Information Technical Support and Product Services MGE Customer Care Center Three Phase ProductsScheduling Field Service Engineer Support Return Policy for Repair of Three Phase Products RGAComet 40-150kVA Term used Definition / Meaning GlossaryFCC NEC This page left blank intentionally Reorder Form Scenic Avenue Costa Mesa, CA Page Page Contact MGE