Toshiba G8000 Series installation manual Unpacking, Points to be observed, UPS Clearance

Page 26

10.1 Unpacking

Make sure that UPS unpacking is conducted on the paved floor indoor, which should be as close as possible to the installing location. A building with overhead traveling cranes is expected to unpack large- sized UPS. If a crane is not available, obtain a wide enough space for forklift operations. Also keep space around the UPS to unpack the crate. Then extract the crate.

Points to be observed

(1)Retain all small articles during unpacking and installation.

(2)Make sure that exterior paint is not scratched and that the UPS cabinet is not damaged.

(3)Do not damage the UPS when using extracting tools.

(4)Do not remove the polyvinyl chloride cover, if provided, until installation.

(5)Packing materials should be disposed by the appropriate means after unpacking.

(6)In case of any abnormalities, immediately report this information to Toshiba or authorized representatives.

10.2UPS Clearance

When the UPS is installed, maintain the clearance around the UPS as shown in Figure 10.1. Ensure that the front and top air vents are NOT blocked.

 

Top: 400mm (15” 3/4)

 

Front:

 

1,100mm

 

(43” 5/16)

Side: 0mm (0”)

Back: 0mm (0”)

Figure 10.1 - UPS Clearance.

25

Image 26
Contents Document Number February Introduction Uninterruptible Power Supply Manual’s Purpose and Scope Contacting Toshiba’s Customer Support CenterGeneral Safety Instructions Important Safety Instructions Safety Precautions General Terms Do not remove the rear/side panels ProhibitedInstallation Precautions Avoid vibration or shock exceeding 0.5G to the UPSUPS Installation Environment Standard Keep the specified clearance around the UPS Keep the UPS room cleanDo not install the UPS close to a water source Connect ground wire to the earth ground terminal only MandatoryLocations of the Warning Labels 100/125 kVA Locations of the Warning Labels 150/180/225 kVA AC Input Grounding Electrode Terminal Contents Dimensions and Weight 100/125kVA UPS Exterior dimensions front & right side150/180/225kVA UPS Exterior dimensions front & right side 250/300kVA UPS Exterior dimensions front & right side Do not expose the UPS to water TransportationAvoid vibration or shock exceeding 0.5 G to the UPS Transportation by a craneAngle more than Transportation by a forklift Storage Installation Ensure that there is adequate working space aroundUPS Clearance UnpackingPoints to be observed Anchor bolts Anchor bolt tighteningExternal Wiring Diagram OverviewTerminal Blocks and Power Cables Phase 3-wire Phase 4-wireRecommended Cable Size and Tightening Torque for 125kVA UPS Recommended Cable Size and Tightening Torque for 180kVA UPS Phase 3-wire Phase 4-wire Recommended Cable Size and Tightening Torque for 250kVA UPS Ilsco External Breakers External Breaker RatingGrounding Wire 100~225kVA 250/300kVAControl Wires 10 External ConnectionsGrounding configuration Recommended configuration with input neutral groundedGrounding configuration without input neutral Recommended configuration with delta-inputGrounding configuration with corner-grounded delta-input 12 Grounding configuration with corner-grounded delta-input