The G8000 UPS units are not equipped with circuit breakers. The electrical contractor should provide the external breakers for AC input, Bypass input, DC input, and AC output. See Figure 11.1 for the position of the breakers.

Table 11.9 shows the minimum rating for each capacity of G8000 UPS breakers. The Bypass input and the AC output require 4-pole breakers.

Table 11.9 External Breaker Rating.

 

AC input / Bypass input / AC output

DC input

Capacity

Minimum Breaker Rating

Minimum Breaker Rating

 

 

 

 

100kVA

480V - 150A

500VDC – 400A

 

 

 

125kVA

380V - 250A

500VDC – 600A

 

 

 

150kVA

480V - 225A

500VDC – 600A

 

 

 

180kVA

380V - 350A

500VDC – 750A

 

 

 

225kVA

480V - 350A

500VDC – 900A

 

 

 

250kVA

380V - 500A

500VDC – 1100A

 

 

 

300kVA

480V - 450A

500VDC – 1,200A

 

 

 

34

Image 35
Contents Document Number February Introduction Uninterruptible Power Supply Contacting Toshiba’s Customer Support Center Manual’s Purpose and ScopeGeneral Safety Instructions Important Safety Instructions Safety Precautions Prohibited General Terms Do not remove the rear/side panelsAvoid vibration or shock exceeding 0.5G to the UPS Installation PrecautionsUPS Installation Environment Standard Keep the specified clearance around the UPS Keep the UPS room cleanDo not install the UPS close to a water source Mandatory Connect ground wire to the earth ground terminal onlyLocations of the Warning Labels 100/125 kVA Locations of the Warning Labels 150/180/225 kVA AC Input Grounding Electrode Terminal Contents 100/125kVA UPS Exterior dimensions front & right side Dimensions and Weight150/180/225kVA UPS Exterior dimensions front & right side 250/300kVA UPS Exterior dimensions front & right side Transportation by a crane TransportationAvoid vibration or shock exceeding 0.5 G to the UPS Do not expose the UPS to waterAngle more than Transportation by a forklift Storage Ensure that there is adequate working space around InstallationUPS Clearance UnpackingPoints to be observed Anchor bolt tightening Anchor boltsOverview External Wiring DiagramPhase 3-wire Phase 4-wire Terminal Blocks and Power CablesRecommended Cable Size and Tightening Torque for 125kVA UPS Recommended Cable Size and Tightening Torque for 180kVA UPS Phase 3-wire Phase 4-wire Recommended Cable Size and Tightening Torque for 250kVA UPS Ilsco External Breaker Rating External Breakers100~225kVA 250/300kVA Grounding Wire10 External Connections Control WiresRecommended configuration with input neutral grounded Grounding configurationRecommended configuration with delta-input Grounding configuration without input neutral12 Grounding configuration with corner-grounded delta-input Grounding configuration with corner-grounded delta-input