Chapter 6: Configurable Settings/Defaults
This section describes the proper setup of the 2 pump,
Many of the variables and setup parameters have been preset at the factory and do not need to be changed. However, this section of the manual will address all of the setup parameters that were available at the time of printing. The purpose of this is to familiarize the reader with all the setup parameters and their usage.
6-1 Station Setup - Factory Presets
Name | Description | Options | Default |
Conveying Options |
|
|
|
Convey time | Length of time the station’s vacuum valve remains | 30 sec. | |
| open to allow material to be drawn in. (For a |
|
|
|
|
| |
| covers the station’s |
|
|
| this time elapses, whichever comes first.) |
|
|
| Adjust this value to match the actual time needed |
|
|
| to fill the station. |
|
|
(Last convey time) | Display only. Length of time the station’s vacuum |
|
|
| valve was open for receiving material during the |
|
|
| most recent convey. This information is displayed | — | — |
| for your reference when adjusting convey time and |
|
|
| dump delay. |
|
|
Dump delay | Length of time allowed for material to drain from | 15 sec. | |
| the station into the receiver. The controller will not |
|
|
| attempt to deliver more material to the station until |
|
|
| this time has elapsed. |
|
|
| Adjust this value to match the actual time needed |
|
|
| to drain the station. If it is set too short, the |
|
|
| controller may attempt to refill the station before it |
|
|
| is empty, causing material to back up and/or |
|
|
| underusing the station’s capacity. If it is set too |
|
|
| long, the system may be unable to keep up with |
|
|
| your equipment’s demand for material. |
|
|
Assigned to pump n | Number (address) of the pump to which this | 0 | |
| station’s vacuum line is connected. | assigned) |
|
Special convey | When this option is enabled, the station’s vacuum | disabled, | disabled |
| valve remains open for the convey time, even if | enabled |
|
| the station is not demanding material and is |
|
|
| indicating that it is full. When disabled, the |
|
|
| station’s vacuum valve opens when there is |
|
|
| demand from the station, and it remains open until |
|
|
| the convey time has elapsed or material trips the |
|
|
|
|
| |
| Enable this option if and only if the station has no |
|
|
| flapper. |
|
|
Hopper Loaders with/without Sight Glasses | 40 |