4.2System Self Diagnostic Test

NOTE: Always run self diagnostic with the intended zero fluid.

1.Press the System button to enter the system mode.

2.Use the < > arrow keys to move to More, and press Enter.

3.Use the < > arrow keys to move to Self-Test, and press Enter. The following failure codes apply:

Table 4-1: Self Test Failure Codes

Power

0OK

15 V Failure

215 V Failures

3Both Failed

Analog

0OK

1DAC A (0–1 V Concentration)

2DAC B (0–1 V Range ID)

3Both Failed

4-2: Part I

Teledyne Analytical Instruments

Image 62
Contents Photometric Analyzer Teledyne Analytical InstrumentsModel 5000B Copyright 1999 Teledyne Analytical InstrumentsTable of Contents IiiModel 5000B Teledyne Analytical Instruments Part I Part I Control UnitOperation InstallationIi Part Maintenance Iv Part Model 5000B Photometric AnalyzerPhotometric Analyzer Part I Control Unit OverviewTypical Applications Introduction Model 5000B Other NIR Absorbers that can be measured consult factory Introduction Model 5000B Main Features of the Analyzer Operator Interface 1 UP/DOWN SwitchESCAPE/ENTER Switch Model 5000B Controls, Indicators, and Connectors Control Section Interface Panel Model 5000B Interface Panel Introduction Model 5000B Installation Unpacking the Control/Analysis UnitPart Primary Input Power Connections 115VACExamples Analog Output ConnectionsAlarm Relays Range Voltage Current mATypes of Relay Contacts The connectors are Part I RS-232 Signals RS-232 Sig RS-232 Pin PurposeParameter Setting Testing the SystemCommand Description Part Operation Photometric Analyzer Operation /Control UnitOperation/Control Unit Hierarchy of System Functions and Subfunctions Setting up an AUTO-CAL System FunctionSelect More and press the Enter Key PasswordProtection Entering the PasswordInstalling or Changing the Password Logging Out System Self-Diagnostic Test Model Screen CheckingLinearitywithALGORITHMDigital Filter Setup Setting 90% Response time secondsFilter or Solenoid Setup Hold/Track Setup Calibration/Hold Timer SetupCalbrt hold 3 min Sample hold 1 min Analog 4 to 20 mA Output CalibrationUse UP/DOWN arrow to Adjust 4 ma 250 ModelZero Cal Auto Mode ZeroingShow Negative Manual Mode Zeroing Cell Failure SccmSpan Cal Auto Mode SpanningManual Mode Spanning How to access the offset function Offset FunctionSelect zero mode Auto Select zero mode MAN Zero off 0.0 ppm ENT to begin ZeroAlarms Function AL1 1ØØØ ppm HI DftN FsN LtchN Range Select Function Manual Select/Define Range ScreenAuto Screen Precautions 2illustratestheseschemesgraphically Analyze Function Set Range Screen Algorithm Application More Curve Algorithm Screen Auto Mode Linearization Fuse Replacement Part I Control Unit/Analysis Unit MaintenancePower System Self Diagnostic TestMaintenance Model 5000B Photometric Analyzer AnalogPreamp Cell detectorPart Part II Part II Analysis UnitRoutine Maintenance Part II Analysis Unit Appendix Iv Part Operations/Analysis Unit Control Functions Explosion-ProofVersionControlModulePreliminaryInspection Control SettingsStart-p Analyzers not equipped with Auto ZeroPower On Observations Pre-Start-upElectricalCheckoutTeledyneAnalyticalInstruments4-5 StandardizationFluids ProcedureCalibration TeledyneAnalyticalInstruments4-7 Operations/Analysis Unit TeledyneAnalyticalInstruments4-9 Operations/Analysis Unit TeledyneAnalyticalInstruments4-11 Operations/Analysis Unit TeledyneAnalyticalInstruments4-13 Ppm simulated water using Span Zero SampleAttachment 5000B/5020 NIR Analyzer Operations/Analysis Unit Operational Theory Contd Source Module OpticalSystem Sample cellAnalyzerSystem-BlockDiagram Power Module Block Diagram Detectorcompartment System Visual Check and Response Procedure Routine MaintenancePart II Maintenance/Analysis Unit Automatic operation and routine operational dutiesSuggested Preventive Maintenance Schedule DailyEquipment Required Oscilloscope Display of the I to E Converter Output Part II Maintenance/Analysis Unit Setup of the Logarithmic Amplifier Inverting AmplifierBattery-Powered Oscilloscope Synchronization Point Interface Board Terminals StripPart Part II Maintenance/Analysis Unit Part Photometric Analyzer, 5000B Appendix SpecificationsOperating Temperature 0-50oC Appendix Models 5000B Other Features Recommended 2-Year Spare Parts List QtyP/NDescriptionDrawing List, 5000B Appendix Models 5000B Teledyne Analytical Instruments