3.Piping Connections

ALL components/materials must conform to National Fuel Gas Code Specifications ANSI Z223.1-LATEST EDITION, or in Canada, CAN/CGA-B149.1-M91 (Natural Gas) or CAN/CGA-B149.2-M91 (Liquid Propane [L.P.] Gas) or LATEST EDITION (for General Installation and Gas Plumbing), as well as local codes and ordinances and must be done by a qualified professional. It is important that gas pressure regulators meet applicable pressure requirements, and that gas meters be rated for the total amount of ALL the appliance BTUs being supplied.

The dryer is provided with two (2) 1-1/4” N.P.T. inlet pipe connections extending out of the top of the burner boxes. The minimum pipe size (supply line) to the dryer is 1-1/2” N.P.T. For ease of servicing, the gas supply line to each dryer must have its own shutoff valve.

The size of the main gas supply line (header) will vary depending on the distance this line travels from the gas meter or, in the case of L.P. gas, the supply tank, other gas-operated appliances on the same supply line, etc,. Specific information regarding supply line size should be determined by the gas supplier.

NOTE: Undersized gas supply piping can create a low or inconsistent pressure which will result in erratic operation of the burner ignition system.

31

Image 35
Contents AD-310 Phase Retain This Manual In a Safe Place For Future Reference Foryour Safety Page Table of Contents Section Burner and Basket TUMBLER/LINT Chamber Manual Reset Receiving and Handling Important InformationWhat to do if YOU Smell GAS Safety PrecautionsStandards Specifications GAS and Steam SPECIFICATIONS/DIMENSIONS Component IdentificationDimensions and Component Location NON-TILT Steam Model Reassembly of Dryer Installation ProceduresPage Lift the basket tumbler section onto the base Page Reassembly Instructions For Non-Tilt Steam Dryers Location Requirements Fresh AIR Supply Requirements Exhaust Requirements Page Page Page Page Page Compressed AIR Supply System Page Page Electrical Requirements Electrical InformationGas Non-Tilt Steam Non-Tilt Page GAS Information Type of GAS Page Water Supply Connection for Optional Sprinkler System Steam Information Operating Steam PressurePage Compressed Air Supply Air Pressure Page Steam Damper Air Piston Flow Control Operation Adjustment Preoperational Tests Natural Gas Inches 8.7 mb water column Liquid Propane L.P Basket Coating Preparation for OPERATION/START-UPShut Down Instructions Parts SERVICE/PARTS InformationService Returning Warranty Parts Warranty InformationReturning Warranty Cards WarrantyPage Suggested Cleaning Schedule Routine MaintenanceCleaning Monthly Lubrication AdjustmentsBasket Tumbler Drive System Component System DescriptionsBasket Tumbler Drive System AIR Blower Drive System Safety DevicesBasket Tumbler Page Steam Damper Actuator System P O R T a N T Phase 7 Steam Models only Data Label Data Label InformationSerial Number Procedure for Functional Check Replacement Components Page Diagnostic L.E.D. Display Fault Messages Phase 7 OPL System DiagnosticsPage O Board Input and Output L.E.D. Indicators Inputs RED Outputs Green RHE PGR1 Green L.E.D OCL5 Green L.E.D No Display TroubleshootingDrive motor is not operating does not start Impellor fan motor is not operating does not start Page Page Dryer operates but is taking too long to dry Excessive noise and vibration Tilt to unload Optional Sprinkler Circuit Components Optional Sprinkler System ComponentsSprinkler and Main Power Connections Sprinkler Option Temperature Controller Settings Page ADC 01/04/00-20 05/07/01-20
Related manuals
Manual 116 pages 19.79 Kb