American Dryer Corp AD-310 Phase 7 Preparation for OPERATION/START-UP, Basket Coating

Page 44

2)Make a complete operational check of ALL safety-related circuits (i.e., lint drawer switch and sail switches on gas models).

3)A reversing basket (tumbler) should never be operated with less than a 100 lb. (45.4 kg.) load (dry weight). The size of the load will affect the coast-down and dwell (stop) times. The basket (tumbler) must come to a complete stop before starting in the opposite direction. For automatic (mode) cycle only, the spin and stop times are not adjustable and have been preprogrammed into the microprocessor controller (computer) for a 2-1/2 minute reverse spin time and a 7-second dwell (stop) time.

BASKET COATING

The basket (tumbler) is treated with a protective coating. We suggest dampening old garments or cloth material with a solution of water and nonflammable mild detergent and tumbling them in the basket (tumbler) to remove this coating.

4)Each dryer should be operated through one (1) complete cycle to assure that no further adjustments are necessary and that ALL components are functioning properly.

5)Microprocessor controller (computer) programs/selections...

a.Each microprocessor controller (computer) has been preprogrammed by the factory with the most commonly used parameter (programs) selections. If computer program changes are required, refer to the computer programming manual which was shipped with the dryer.

K.PREPARATION FOR OPERATION/START-UP

The following items should be checked before attempting to operate the dryer:

1.Read ALL “CAUTION,” “WARNING,” and “DIRECTION” labels attached to the dryer.

2.Check incoming supply voltage to be sure that it is the same as indicated on the dryer data label affixed behind the right control box door. In case of 208 VAC, for dryers with sprinkler option, verify single-phase (1ø) voltage is correct. The supply voltage must match the electrical service exactly.

3.GAS MODELS - check to assure that the dryer is connected to the type of heat/gas indicated on the dryer data label.

4.GAS MODELS - the sail switch damper assembly was installed and adjusted at the factory prior to shipping. However, each sail switch adjustment must be checked to assure that this important safety control is functioning.

5.GAS MODELS - be sure that ALL gas shutoff valves are in the open position.

6.Be sure ALL side and base panels are on the dryer.

7.Check ALL service doors to assure that they are closed and secure.

8.Be sure lint drawer is securely in place.

40

Image 44
Contents AD-310 Phase Retain This Manual In a Safe Place For Future Reference Foryour Safety Page Table of Contents Section Burner and Basket TUMBLER/LINT Chamber Manual Reset Important Information Receiving and HandlingSafety Precautions What to do if YOU Smell GASStandards SPECIFICATIONS/DIMENSIONS Component Identification Specifications GAS and SteamDimensions and Component Location NON-TILT Steam Model Installation Procedures Reassembly of DryerPage Lift the basket tumbler section onto the base Page Reassembly Instructions For Non-Tilt Steam Dryers Location Requirements Fresh AIR Supply Requirements Exhaust Requirements Page Page Page Page Page Compressed AIR Supply System Page Page Electrical Information Electrical RequirementsGas Non-Tilt Steam Non-Tilt Page GAS Information Type of GAS Page Water Supply Connection for Optional Sprinkler System Operating Steam Pressure Steam InformationPage Compressed Air Supply Air Pressure Page Steam Damper Air Piston Flow Control Operation Adjustment Preoperational Tests Natural Gas Inches 8.7 mb water column Liquid Propane L.P Preparation for OPERATION/START-UP Basket CoatingShut Down Instructions Parts SERVICE/PARTS InformationService Warranty Information Returning Warranty CardsWarranty Returning Warranty PartsPage Suggested Cleaning Schedule Routine MaintenanceCleaning Monthly Adjustments LubricationBasket Tumbler Drive System Component System DescriptionsBasket Tumbler Drive System AIR Blower Drive System Safety DevicesBasket Tumbler Page Steam Damper Actuator System P O R T a N T Phase 7 Steam Models only Data Label Information Data LabelSerial Number Procedure for Functional Check Replacement Components Page Phase 7 OPL System Diagnostics Diagnostic L.E.D. Display Fault MessagesPage O Board Input and Output L.E.D. Indicators Inputs RED Outputs Green RHE PGR1 Green L.E.D OCL5 Green L.E.D Troubleshooting No DisplayDrive motor is not operating does not start Impellor fan motor is not operating does not start Page Page Dryer operates but is taking too long to dry Excessive noise and vibration Tilt to unload Optional Sprinkler System Components Optional Sprinkler Circuit ComponentsSprinkler and Main Power Connections Sprinkler Option Temperature Controller Settings Page ADC 01/04/00-20 05/07/01-20