Centurion CP72SR5 installation manual ANTI-LIFT Brackets

Page 5

ANTI-LIFT BRACKETS

-Guide rollers 39 must ensure that the gate is held vertically.

-Fit suitable anti-lift brackets 42. The gap 40 should be <5mm to ensure the gate cannot be lifted off the motor pinion.

-For improved safety fit additional support post 41 to prevent gate from falling over if guide rollers 39 fail.

3

Image 5
Contents Sliding Gate Automation Page Major Components Typical D5 Shown Oil Specifications Grade 75W90 Qty 75mlStart kgF RUN kgF Gate Mass kg 300 500 ANTI-LIFT Brackets Duty Cycle Curves Recommended Installation and Cable Thickness REQUIREMENTS† Option 1 Bolt down onto concrete plinth Mechanical Mounting DetailsPage Option 2 Set into concrete plinth Provision for Cables Gearbox Mounting Down Details Useful TIP Mounting Rack200mm Installing Chain Drive Systems Ensure fan has stopped turning Setting Mechanical Clutch A5 onlyMounting of Gate Sensor Mounting Configuration For Steel RackRemovable Connectors Power Wiring see page 15 for Signal WiringSignal Wiring CP80 and CP81 Recommended Lightning Protection Commissioning Block Diagram Gate Closes Towards Left Above Black Blue RED Towards Right Setting Motor DirectionSelecting Programme Mode A5 only Setting Gate LimitsStart Automated Gate Limits Routine Setting Gate LimitsD3/D5 Motor Automatic SET-UP Start Manual Gate Limits Routine Exit Gate Limits Routine D3/D5 onlyA5 Motor Manual SET-UP Align Origin SwitchFunctions Select Exit Gate Limits Routine A5 onlyFactory Defaults Highlighted Timer and Counter Setting Main Unit Menu Measure Fault Finders Guide D3 / D5 Operators Procedure to Programme Controller Back to Factory SettingsGate Opens to Pedestrian and Closes Page Centurion