Heat Controller HTV Water Tank Preparation, Initial Start-Up, HWG Water Piping, Water Tank Refill

Page 18

Installation, Operation & Maintenance

HTV/HTD/HTH SERIES

Heat Controller, Inc.

Hot Water Generator

Warning! The HWG pump Is fully wired from the factory. Use extreme caution when working around the microprocessor control as it contains line voltage connections that presents a shock hazard that can cause severe injury or death!

The heat pump, water piping, pump, and hot water tank should be located where the ambient temperature does not fall below 50°F [10°C]. Keep water piping lengths at a minimum. DO NOT use a one way length greater than 50 ft. (one way) [15 m]. See Table 7 for recommended piping sizes and maximum lengths.

All installations must be in accordance with local codes. The installer is responsible for knowing the local requirements, and for performing the installation accordingly. DO NOT connect the pump wiring until “Initial Start-Up” section, below. Powering the pump before all installation steps are completed may damage the pump.

Water Tank Preparation

1.Turn off power or fuel supply to the hot water tank.

2.Connect a hose to the drain valve on the water tank.

3.Shut off the cold water supply to the water tank.

4.Open the drain valve and open the pressure relief valve or a hot water faucet to drain tank.

5.When using an existing tank, it should be flushed with cold water after it is drained until the water leaving the drain hose is clear and free of sediment.

6.Close all valves and remove the drain hose.

7.Install HWG water piping.

insure maximum utilization of the heat available from the refrigeration system and conserve the most energy. On tanks with both upper and lower elements and thermostats, the lower element should be turned down to 100°F [38°C] or the lowest setting; the upper element should be adjusted to 120-130°F [49-54°C]. Depending upon the specific needs of the customer, you may want to adjust the upper element differently. On tanks with a single thermostat, a preheat tank should be used (Fig 15).

6.Replace access cover(s) and restore power or fuel supply.

Initial Start-Up

1.Make sure all valves in the HWG water circuit are fully open.

2.Turn on the heat pump and allow it to run for 10-15 minutes.

3.Set SW12 to the “OFF” position (enabled) to engage the HWG.

4.The HWG pump should not run if the compressor is not running.

5.The temperature difference between the water entering and leaving the HWG coil should be approximately 5-10°F [3- 6°C].

6.Allow the unit to operate for 20 to 30 minutes to insure that it is functioning properly.

HWG Water Piping

1.Using at least 5/8” [16mm] O.D. copper, route and install the water piping and valves as shown in Figures 14 or 15. Install an approved anti-scald valve if the 150°F HWG setpoint is or will be selected. An appropriate method must be employed to purge air from the HWG piping. This may be accomplished by flushing water through the HWG (as In Figures 14 and

15) or by Installing an air vent at the high point of the HWG piping system.

2.Insulate all HWG water piping with no less than 3/8” [10mm] wall closed cell insulation.

3.Open both shut off valves and make sure the tank drain valve is closed.

Water Tank Refill

1.Close valve #4. Ensure that the HWG valves (valves #2 and #3) are open. Open the cold water supply (valve #1) to fill the tank through the HWG piping. This will purge air from the HWG piping.

2.Open a hot water faucet to vent air from the system until water flows from faucet; turn off faucet. Open valve #4.

3.Depress the hot water tank pressure relief valve handle to ensure that there is no air remaining in the tank.

4.Inspect all work for leaks.

5.Before restoring power or fuel supply to the water heater, adjust the temperature setting on the tank thermostat(s) to

Table 7: HWG Water Piping Sizes and Length

Unit

Nominal

1/2" Copper

3/4" Copper

Nominal

HWG Flow

(max length*)

(max length*)

Tonnage

(gpm)

 

 

1.5

0.6

50

-

 

 

 

 

2.0

0.8

50

-

 

 

 

 

2.5

1.0

50

-

 

 

 

 

3.0

1.2

50

-

 

 

 

 

3.5

1.4

50

-

 

 

 

 

4.0

1.6

45

50

 

 

 

 

5.0

2.0

25

50

 

 

 

 

6.0

2.4

10

50

*Maximum length is equivalent length (in feet) one way of type L copper.

18

Image 18
Contents HTV/HTD/HTH Series Two-Stage Geothermal Heat Pumps To 6 Tons Table of Contents Safety General Information Horizontal Unit Location Hanger BracketHorizontal Installation Typical Horizontal Unit InstallationField Conversion of Air Discharge Side to Back Discharge ConversionDuct System Installation Condensate Piping Horizontal Unitsರ3HU RRW Vertical Installation Vertical Unit LocationReturn Using a threaded pipe or similar device to clearMay ease final drain line installation Air InletExternal Flow Controller Mounting Water Connection InstallationPiping Installation Flushing the Earth LoopFluid Volume gal liters per 100’ 30 meters Pipe Ground-Loop Heat Pump ApplicationsAntifreeze Water Quality Standards Antifreeze Percentages by VolumeOpen Loop Ground Water Systems Pressure Tank and PumpGround-Water Heat Pump Applications Typical Open Loop/Well ApplicationWater Quality Standards Typical HWG Installation Hot Water GeneratorControl Logic Error InstallationHigh Water Temperature 160ºF ÅashesHWG Water Piping Water Tank PreparationInitial Start-Up Water Tank RefillElectrical Line Voltage HT Series Electrical DataHWG Wiring Split Units Only General Line Voltage WiringPower Connection Electrical Line VoltageLow Water Temperature Cutout Selection Electrical Low Voltage WiringLow voltage Äeld wiring for units with ECM fan Thermostat ConnectionsAccessory Connections Two-stage UnitsFault LED Electrical Thermostat WiringThermostat Installation ATM21U01ECM Blower Control ECM Board Tap Settings HT UnitsHT Series ECM Blower Performance Data CXM Controls Safety Features CXM Control Diagnostic FeaturesUnit Operation Stat signal CXM Control Start-up OperationECM fan PSC fan CXM Thermostat Details Nominal resistance at various temperaturesThermostat Signals Not compatible with the CXMCommissioning Conditions Unit Commissioning And Operating ConditionsOperating Limits Voltage utilization range complies with Ahri StandardUnit Start-Up and Operating Conditions Before Powering SYSTEM, please check the followingUnit Start-up Procedure Unit and System CheckoutUnit Start-Up Procedure HT Coax Water Pressure Drop Water Temperature Change Through Heat ExchangerUnit Operating Conditions Antifreeze Correction TableHT Series Typical Unit Operating Pressures and Temperatures PsigGPM Performance Data HT 024 Full Load Cooling EAT 80/67FPerformance Data HT 036 Full Load Performance Data HT 048 Full Load Performance Data HT 060 Full Load Performance Data HT 070 Full Load Preventive Maintenance Troubleshooting CXM Functional Troubleshooting Flow Chart CXM Process Flow ChartFunctional Troubleshooting Main power problemsPerformance Troubleshooting Performance Troubleshooting Htg Clg Possible Cause SolutionTroubleshooting Form +&$97B00