TEST BUTTON

The specifications of the earth leakage breaker :

zRated Sensitive Current: 30mA (or below) (Grounding resistance: 500Ω or below)

zSensitive time: Within 0.1second

5-3.1 Grounding Work

The qualified electrician should perform the grounding work of the following 3 points (500Ω or below).

zThe earth grounding terminal in the output terminals

zThe Outer Bonnet (Canopy) of the generator

zThe Outer Bonnet of the load

<Caution>

zIn the event you cannot ground the generator to the earth, consult with the authorized dis- tributor or our engineering section.

DGW311DM

DGW311L

EARTH GROUNDING TERMINAL

EARTH GROUNDING TERMINAL

 

BONNET GROUNDING

BONNET GROUNDING

TERMINAL

TERMINAL

 

GROUNDING ROD

GROUNDING ROD

5-3.2 Operation Check

Before operating the generator, check always if the device can work. RESET BUTTON EARTH LEAKAGE

INDICATION LAMP

Turn the starter switch from STOP to Run.

Turn (Push-up) the circuit breaker (lever) to ON position.

Push the test button. (When the button is pushed, the earth leakage indication lamp turns ON and the circuit breaker is po- sitioned in the middle of ON and OFF positions, the device can

work normal.)

Push the reset button. (The earth leakage indication lamp (red) turns OFF subsequently.)

Turn (push down) the circuit breaker (lever) to OFF position.

Restore the switch to STOP. <Caution>

z In the event you cannot complete every step of the above procedure to the end, the device is out of order. Consult with our authorized distributor or our engineering section to repair.

10

Image 11
Contents DGW311DM DGW311L Introduction Safety Guidelines Page DGW311DM DGW311L DGW311DM DGW311L SpecificationsParts UseEquipment ECO Welding DGW311DM only Monitor Lamp Earth Leakage Breaker Earth Grounding Terminal Bonnet Grounding Grounding ROD Checking Engine Oil Slow-Down FeatureInitialization and Pre-check Checking Coolant/Water SAE10W/30Checking Fuel Lowest Ambient Temperature Mixture Ratio 30% 35% 45%Operation Initializing/Preparation Checking BatteryChecking Fuel, Engine Oil and Water Leakage ⑧ Keep the engine idle for about 5 minutes IshesWelding Operation Selection Welding Cable „ Restart after stopping due to fuel shortageStopping Generator/Welder ECO Single Dual Welding Rod Φ2.0 φ4.0 Φ2.6 φ6.0 PolarityConnection Welding Cable Welding Duty CycleMaximum output from the terminals U, V, W is 10kVA 『DUAL 』35-280A45-310A φ2.0-φ6.0 380V 400V 415V 380V 400V 415V 2.2 1-Phase Output TerminalsOutput Limitation Operation Simultaneous Use of Welding and Generating Checking and Maintenance 50hrs Clean/Change Fuel FilterAdjust Tension V-Belt Adjust Engine Valve ClearanceRemove the cup and fuel filter element Turn the fuel line valve lever to 『CLOSE』Unscrew the retaining ring by turning counterclockwise, Long Term Storage Excessive Welding Arc TroubleshootingInsufficient Fuel Water or contaminants in fuelEngine does not stop Stop Solenoid disorder No AC outputAC Output is Weak Slow-Down does not activateDGW311L DGW311DM Engine Wiring DiagramGenerator Wiring Diagram DGW311L W220B DGW311L W380A DGW311L W400A DGW311L W415A Telephone 81-82-849-2220 FAX