Cisco Systems 9001S, ASR9001s manual Rack-Mounting the Router Chassis, Verifying Rack Dimensions

Page 42

Chapter 2 Unpacking and Installing the Chassis

Rack-Mounting the Router Chassis

Rack-Mounting the Router Chassis

The router chassis is installed in a front-mounted position, as shown in Figure 1-7for the

Cisco ASR 9001 Router chassis.

In a front-mounted position, the chassis rack-mounting flanges are secured directly to the rack posts.

The PID of the rack mounting kit for Cisco ASR 9001 Router and Cisco ASR 9001-S Router is ASR-9001-2P-KIT=.

Verifying Rack Dimensions

Before you install the chassis, measure the space between the vertical mounting flanges (rails) on your equipment rack to verify that the rack conforms to the measurements shown in Figure 2-2.

Step 1 Mark and measure the distance between two holes on the left and right mounting rails.

The distance should measure 18.31 inches ± 0.06 inches (46.5 cm ± 0.15 cm).

Note Measure the distance for pairs of holes near the bottom, middle and top of the equipment rack to ensure that the rack posts are parallel.

Step 2 Measure the space between the inner edges of the left front and right front mounting flanges on the equipment rack.

The space must be at least 17.7 inches (45 cm) to accommodate the chassis, which is approximately 17.45 in. (44.32 cm) wide, and fits between the mounting posts on the rack.

Figure 2-2 Verifying Equipment Rack Dimensions

Mounting flanges

Minimum usable

aperture 17.7 inches

(45.0 cm)

Hole centerline

to hole centerline

18.31inches ± 0.06 inches (46.5 cm ± 0.15 cm)

247170

Installing the Chassis in a 2-Post Rack

Two people must lift the router chassis using the handles on the sides. To accommodate racks with different hole patterns in their mounting flanges, the chassis rack-mounting flanges have three oblong screw holes on each side.

Cisco ASR 9001 and Cisco ASR 9001-S Routers Hardware Installation Guide

2-4

OL-26701-02

 

 

Image 42
Contents Americas Headquarters Text Part Number OL-26701-02Page Cisco ASR 9001 Router Cable Management Status LEDs Site Log B-1 Purpose Changes to This DocumentAudience Revision Date Change SummaryDocument Organization Document ConventionsObtaining Documentation and Submitting a Service Request OL-26701-02 Preparing for Installation Safety Guidelines General Safety GuidelinesCompliance and Safety Information Laser SafetyEnergy Hazard Preventing Electrostatic Discharge Damage Lifting GuidelinesSite Layout and Equipment Dimensions Site Requirement GuidelinesRear of chassis Site Wiring Guidelines Chassis Air Flow GuidelinesRack-Mounting and Air Flow Clearance Guidelines Air exhaust Room airTelco 2-Post Rack Equipment Rack TypesOpen 4-Post Rack Enclosed Rack with Perforated SidesAir Flow Guidelines for Enclosed Rack Installation Temperature and Humidity Guidelines Power Connection GuidelinesAC Powered Routers AC Power Cord IllustrationsAC Power Cord CAB-AC 12 AC Power Cord CAB-ACI 15 AC Power Cord CAB-ACU DC Powered Router 18 AC Power Cord CAB-9K10A-EU20 DC Power Cable Terminal Block 331933 Nebs Supplemental Unit Bonding and Grounding Guidelines Cisco ASR 9001 Router Port Connection Guidelines 23 Cisco ASR 9001 Router Front Panel PortsMLT3 Port NameDescription SMBConsole Port Signals Signal Input/Output DescriptionConsole Port and Auxiliary Port Connection Guidelines Auxiliary Port Signals 10Base-T, 100Base-TX Signal 1000Base-T SignalManagement LAN Ports Connection Guidelines Management LAN Port LED Indicators Management LAN RJ-45 CablingSync Port LED Indicators Sync Ports Connection GuidelinesPin Signal RP External USB PortOL-26701-02 Pre-Installation Considerations and Requirements Installation OverviewUnpacking the Cisco ASR 9001 Router Required Tools and EquipmentPositioning the Router Verifying Rack Dimensions Installing the Chassis in a 2-Post RackRack-Mounting the Router Chassis Page Correct Lifting Positions Installing the Chassis in a 4-post Rack Supplemental Bonding and Grounding ConnectionsNebs Bonding and Grounding for the Cisco ASR 9001 Router Installing Modules and Cables in the Chassis Fixed 4x10-Gigabit Ethernet PortsModular Port Adapters Port Gigabit Ethernet Modular Port AdapterPort 10 Gigabit Ethernet Modular Port Adapter LED Label Color State MeaningStatus 4-Port 10 Gigabit Ethernet Modular Port Adapter Installing and Removing Modular Port Adapters 2-Port 10 Gigabit Ethernet Modular Port AdapterHandling Modular Port Adapters MPAs Online Insertion and RemovalModular Port Adapter MPA Installation and Removal GE MPACleaning Optical Devices Optical Device Installation and RemovalChecking the Installation Verifying the InstallationPage Using the ping Command to Verify Network Connectivity Command Type of Information ProvidedInstalling and Removing SFP Modules Installing and Removing XFP ModulesInstalling a Cable Management Tray Cable ManagementCable Management Tray Cable-Management Tray Installation and Removal Removing a Cable-Management TrayInstalling a Cable Management Bracket Cable Management BracketCable-Management Bracket Installation and Removal Removing a Cable-Management BracketConnecting Route Processor Cables 10 RP Console and Auxiliary Port ConnectionsConnecting to the RP Console Port Connecting to the RP Auxiliary PortConnecting to the RP Ethernet Management Ports Connecting Power to the Router Connecting Power to an AC-Powered RouterProceed to the Powering on the Router section on Connecting Power to a DC-Powered Router Negative to negativePowering on the Router 12 Typical Power Connections for a Single DC Power ModuleOL-26701-02 Troubleshooting Overview Troubleshooting Using a Subsystem ApproachIdentifying Startup Issues Normal Router Startup SequenceTroubleshooting the Power Subsystem Troubleshooting the AC-Input Power SubsystemPower Module Status Indicators LEDTroubleshooting the DC-Input Power Subsystem Troubleshooting a DC Power ModuleHardware and Software Identification Additional Power Subsystem Troubleshooting InformationObtaining Temperature and Environmental Information Hardware IDTroubleshooting the Installation Troubleshooting the Power Distribution System 8VLGTNGTroubleshooting the Route Processor Subsystem Route Processor OverviewRP Front Panel Indicators Indicator LabelColor Description Ethernet Ports and Status LEDs Auxiliary and Console PortsInitial Boot Process Troubleshooting the Line CardMonitoring Critical, Major, and Minor Alarm Status Status LEDsParameter Configuration File Entry Default Value Configuring and Troubleshooting Line Card InterfacesConfiguration Parameters MTUUsing Configuration Commands Basic Line Card ConfigurationLine Card Interface Address Verifying the Transceiver Modules PID XFP-10G-MM-SR Advanced Line Card Troubleshooting Show logging Show diag slot Show context location slotTroubleshooting the Cooling Subsystem Power Module FansFan Tray Operation Over-temperature Conditions Isolating Cooling Subsystem ProblemsOL-26701-02 Prerequisites and Preparation Field Replaceable UnitsPowering Off the Router Removing and Replacing the Fan TrayRemoving and Replacing AC or DC Power System Components Power Module Replacement Guidelines Removing and Replacing an AC or DC Power ModuleRemoving an AC or DC Power Module Installing an AC or DC Power Module Removing a Chassis from the Equipment RackInstalling a Replacement Chassis in the Equipment Rack Packing a Chassis for ShipmentTechnical Specifications Description Value Table A-3 Cisco ASR 9001 AC Electrical Specifications Minimum Maximum Range Nominal Range Minimum Nominal MaximumParameter Value Typical Maximum Part Number Description Wavelength Fiber Type DistancePart Number Description Part Number Description Wavelength Color IdentifierITU Grid Part Number Description Wavelength ITU Grid XFP-10GZR-OC192LR Fiber Type DistanceXFP-10GLR-OC192SR XFP-10G-MM-SRDWDM-XFP-C OL-26701-02 Site Log Appendix B Site Log Numerics IN-2 See EMI EMIACT CwdmLED Dwdm LinkNebs IN-5IN-6 IN-7 IN-8