Cisco Systems ASR9001s, 9001S manual Removing a Cable-Management Bracket

Page 61

Chapter 3 Installing Modules and Cables in the Chassis

Cable Management

Figure 3-9 Cable-Management Bracket Installation and Removal

1

332146

1

Cable-Management Bracket

Step 3 Insert and tighten the captive screw(s) to secure the bracket. (see Figure 3-9).

Step 4 Connect all the cables to the intended ports and pass them throught the cable management bracket in an organized manner.

Removing a Cable-Management Bracket

To remove a cable-management bracket, follow these steps (see Figure 3-9):

Step 1 Attach an ESD-preventive wrist or ankle strap and follow its instructions for use.

Step 2 Note the current interface cable connections to the ports on the RP.

Step 3 Starting with the interface cable for the bottom port on the RP, disconnect the cable from the RP interface.

Step 4 Repeat Step 3 for all remaining interface cables, proceeding from the bottom ports upward, then proceed to Step 5.

Step 5 Loosen the captive installation screw on the cable-management bracket and remove the bracket from the chassis (see Figure 3-9).

 

 

Cisco ASR 9001 and Cisco ASR 9001-S Routers Hardware Installation Guide

 

 

 

 

 

 

OL-26701-02

 

 

3-15

 

 

 

 

 

Image 61
Contents Text Part Number OL-26701-02 Americas HeadquartersPage Cisco ASR 9001 Router Cable Management Status LEDs Site Log B-1 Audience Changes to This DocumentPurpose Revision Date Change SummaryDocument Conventions Document OrganizationObtaining Documentation and Submitting a Service Request OL-26701-02 Preparing for Installation General Safety Guidelines Safety GuidelinesLaser Safety Compliance and Safety InformationEnergy Hazard Lifting Guidelines Preventing Electrostatic Discharge DamageSite Requirement Guidelines Site Layout and Equipment DimensionsRear of chassis Chassis Air Flow Guidelines Site Wiring GuidelinesAir exhaust Room air Rack-Mounting and Air Flow Clearance GuidelinesEquipment Rack Types Telco 2-Post RackEnclosed Rack with Perforated Sides Open 4-Post RackAir Flow Guidelines for Enclosed Rack Installation Power Connection Guidelines Temperature and Humidity GuidelinesAC Power Cord Illustrations AC Powered RoutersAC Power Cord CAB-AC 12 AC Power Cord CAB-ACI 15 AC Power Cord CAB-ACU 18 AC Power Cord CAB-9K10A-EU DC Powered Router20 DC Power Cable Terminal Block 331933 Nebs Supplemental Unit Bonding and Grounding Guidelines 23 Cisco ASR 9001 Router Front Panel Ports Cisco ASR 9001 Router Port Connection GuidelinesDescription Port NameMLT3 SMBSignal Input/Output Description Console Port SignalsConsole Port and Auxiliary Port Connection Guidelines 10Base-T, 100Base-TX Signal 1000Base-T Signal Auxiliary Port SignalsManagement LAN Ports Connection Guidelines Management LAN RJ-45 Cabling Management LAN Port LED IndicatorsSync Ports Connection Guidelines Sync Port LED IndicatorsRP External USB Port Pin SignalOL-26701-02 Installation Overview Pre-Installation Considerations and RequirementsRequired Tools and Equipment Unpacking the Cisco ASR 9001 RouterPositioning the Router Installing the Chassis in a 2-Post Rack Verifying Rack DimensionsRack-Mounting the Router Chassis Page Correct Lifting Positions Supplemental Bonding and Grounding Connections Installing the Chassis in a 4-post RackNebs Bonding and Grounding for the Cisco ASR 9001 Router Fixed 4x10-Gigabit Ethernet Ports Installing Modules and Cables in the ChassisPort Gigabit Ethernet Modular Port Adapter Modular Port AdaptersLED Label Color State Meaning Port 10 Gigabit Ethernet Modular Port AdapterStatus 4-Port 10 Gigabit Ethernet Modular Port Adapter 2-Port 10 Gigabit Ethernet Modular Port Adapter Installing and Removing Modular Port AdaptersOnline Insertion and Removal Handling Modular Port Adapters MPAsGE MPA Modular Port Adapter MPA Installation and RemovalChecking the Installation Optical Device Installation and RemovalCleaning Optical Devices Verifying the InstallationPage Command Type of Information Provided Using the ping Command to Verify Network ConnectivityInstalling and Removing XFP Modules Installing and Removing SFP ModulesCable Management Installing a Cable Management TrayCable Management Tray Removing a Cable-Management Tray Cable-Management Tray Installation and RemovalCable Management Bracket Installing a Cable Management BracketRemoving a Cable-Management Bracket Cable-Management Bracket Installation and Removal10 RP Console and Auxiliary Port Connections Connecting Route Processor CablesConnecting to the RP Auxiliary Port Connecting to the RP Console PortConnecting to the RP Ethernet Management Ports Connecting Power to an AC-Powered Router Connecting Power to the RouterProceed to the Powering on the Router section on Negative to negative Connecting Power to a DC-Powered Router12 Typical Power Connections for a Single DC Power Module Powering on the RouterOL-26701-02 Troubleshooting Using a Subsystem Approach Troubleshooting OverviewNormal Router Startup Sequence Identifying Startup IssuesTroubleshooting the AC-Input Power Subsystem Troubleshooting the Power SubsystemLED Power Module Status IndicatorsTroubleshooting a DC Power Module Troubleshooting the DC-Input Power SubsystemObtaining Temperature and Environmental Information Additional Power Subsystem Troubleshooting InformationHardware and Software Identification Hardware IDTroubleshooting the Installation 8VLGTNG Troubleshooting the Power Distribution SystemRoute Processor Overview Troubleshooting the Route Processor SubsystemIndicator Label RP Front Panel IndicatorsColor Description Auxiliary and Console Ports Ethernet Ports and Status LEDsMonitoring Critical, Major, and Minor Alarm Status Troubleshooting the Line CardInitial Boot Process Status LEDsConfiguration Parameters Configuring and Troubleshooting Line Card InterfacesParameter Configuration File Entry Default Value MTUBasic Line Card Configuration Using Configuration CommandsLine Card Interface Address Verifying the Transceiver Modules PID XFP-10G-MM-SR Show logging Show diag slot Show context location slot Advanced Line Card TroubleshootingPower Module Fans Troubleshooting the Cooling SubsystemFan Tray Operation Isolating Cooling Subsystem Problems Over-temperature ConditionsOL-26701-02 Field Replaceable Units Prerequisites and PreparationRemoving and Replacing the Fan Tray Powering Off the RouterRemoving and Replacing AC or DC Power System Components Removing and Replacing an AC or DC Power Module Power Module Replacement GuidelinesRemoving an AC or DC Power Module Removing a Chassis from the Equipment Rack Installing an AC or DC Power ModulePacking a Chassis for Shipment Installing a Replacement Chassis in the Equipment RackTechnical Specifications Description Value Table A-3 Cisco ASR 9001 AC Electrical Specifications Range Minimum Nominal Maximum Minimum Maximum Range NominalParameter Value Part Number Description Wavelength Fiber Type Distance Typical MaximumPart Number Description Color Identifier Part Number Description WavelengthITU Grid Part Number Description Wavelength ITU Grid XFP-10GLR-OC192SR Fiber Type DistanceXFP-10GZR-OC192LR XFP-10G-MM-SRDWDM-XFP-C OL-26701-02 Site Log Appendix B Site Log Numerics IN-2 EMI See EMILED Dwdm CwdmACT LinkIN-5 NebsIN-6 IN-7 IN-8