7.0 INSTALLATION

For technical information see section 8.0.

7.1 LOCATION IN PLANT

Ensure that the correct tie down points are used.

For major overhaul (i.e. motor removal) position the machine to obtain lifting access e.g. fork lift truck.

See diagram in reference section for minimum space requirements for normal operation and maintenance.

Ambient temperatures higher than 46° C (115° F) must be avoided as well as areas of high humidity.

Consider also the environment surrounding or near the compressor. The area selected for the location of the compressor should be free of dust, chemicals, metal filings, paint fumes and overspray.

Hard surfaces may reflect noise with an apparent increase in the decibel level. When sound transmission is important, a sheet of rubber or cork can be installed beneath the machine to reduce noise. Flexible piping may be required.

It is recommended that provision be made for lifting heavy components during major overhaul. Use only lifting points provided.

Minimum space in front of control panel door as required by National or Local codes must be maintained.

The compressor can be installed on any level floor capable of supporting it. A dry, well ventilated area where the atmosphere is as clean as possible is recommended.

Sufficient space all round and above the compressor must be allowed, to enable the effective removal of the cooling air which, in turn, will reduce the risk of recirculating the cooling air back through the compressor.

caution

A minimum of 1 m (3.3ft) all round the compressor is recommended. If headroom is restricted, then the ex- haust should be ducted or deflected away from the machine.

Screw type compressors [1] should not be installed in air systems with reciprocating compressors without means of isolation such as a common receiver tank. It is recommended that both types of compressor be piped to a common receiver using individual air lines.

The machine is shipped with the shipping restraints in place. Ensure that these are removed to allow free movement of the drive assembly during operation. Each restraint is painted yellow.

IRN37 - 160K - CC & IRN50 - 200H & IRN75 - 160K - 2S & IRN - 100 - 200H - 2S & IRN 250 - 300H - 2S

19

http://air.irco.com

 

Image 21
Contents Operation and Maintenance Manual AIR Compressor Group Bonded Warranty & Registered Start UP Contents Foreword If in Doubt Consult SupervisionSomer FOREWORD Energy recovery system Abbreviations & SymbolsERS F.CPurchase Order Details Rotary Screw AIR CompressorThis unit was purchased from Safety General InformationCompressed air Avoid INGESTION, Skin Contact Inhalation of Fumes MaterialsTransport ElectricalCoolant disposal Condensate disposalDischarge air Text DecalsLift here 39540257 Rev RotationCondensate Drain Electrical power inlet Prohibition / Mandatory Information / Instructions Safety Graphic Form and Meaning of ISO SymbolsDo not stand on any service valve or Safety Coolant Separator Pressure AIR Discharge Belt Tension Filter Motor Lubrication Receipt Receipt / HandlingIngersoll Rand Company Unpacking and HandlingLocation in Plant InstallationFor technical information see section Ensure that the correct tie down points are usedInstallation Discharge and Condensate Piping Installation Electrical Installation Very Important Fuse TypeExample of voltage imbalance calculation Cooling Water Piping Adjusting the Aftercooler Trim ValveModel Minimum cooling water requirement vs Range 50F 70FWater quality recommendations Installation SEA Watercooled Units Selected Units only Orifice diameter in mmPsi Outdoor Sheltered Installation Technical INFORMATION-SINGLE Stage General InformationCooling clean water flow l/min US 51/38 95/46 Minimum ambient temperature C F Weight Kg lbsSound pressure level dBA Flow at 7.5 Barg m3/minMax fuse size @ 380V − 415V a Cooling clean water flow l/min US 84/65 95/72Max fuse size @ 440V − 480V a Max fuse size @ 550V − 575V aN132K N160K N200H General Information Technical Information − TWO Stage Flow at 100 psig cfm 1100 59331690 1527KEY Installation DRAWING−N37/45K−CC & N50/60H−CC − Air CooledInstallation DRAWING− N37/45K−CC & N50/60H−CC − Water Cooled Installation Drawing − N55/75K−CC & N75/100H−CC − Air Cooled Installation DRAWING−N55/75K−CC & N75/100H−CC−Water Cooled General Information General Information General Information General Information KEY 22381206 Revision B Equipment downstream of compressor Stage only 23128994 Revision aAir/coolant Coolant Condensate Cooling water W.C. only 22099006 Revision C General Information 22402135 Revision C Process and Instrumentation Diagram N250−300H TWO StagePiping legend Stop FD Wiring Schematic N37K − N45K-CC / N50-60h−cc a/c blower vfdNumbers Function Wire color WiresLabel Description Wiring schematic n55-75k-cc / n75-100h-cc a/c Blower vfdSS1-3 Wires Numbers Function Wire colorSgne Wiring schematic n37/45k-cc/n50/60h-cc w/cColor 23131345 Revision a Wiring schematic n55-75k-cc / n75-100h-cc W/c4ATT SENSOR, Package AIR Discharge Temperature 4CTT Wiring schematic n75-160k-cc / n125-200h-cc A/c 22093058Revision M SGNe F10Revision E Wiring schematic n75-160k-cc / n125-200h-cc W/c4SV VALVE, Water Stop 6APT 380-480V SG-Ne Wiring schematic n250-300H4ATT SENSOR, Package AIR Discharge Temperature 6APT General Information General Description Basic Operation Operating InstructionsStopping the machine in an emergency Arrows Intellisys ControlsMain Menu Display ScreenCurrent Status items Current Status ScreenReady to Start Main MenuOperator Setpoints Operator Setpoints Default MIN MAX Step UnitCondensate Interval Selection MIN MAX OptionsScheduled start Sensor CalibrationClock Functions Alarm HistoryEnergy Status Messages Initial Check Alarms Service WarningsAlarm Main Menu AlarmsMaintenance Ultra Coolant Maintenance Procedures Prior to attempting any maintenance work, ensure that− Adding coolant Prior to starting Coolant level checking procedureSeparator element checking procedure Coolant filter change procedureSeparator element change procedure Drain sequence for N250/300H−2SScavenge screen clean/check procedure Separator element change procedure for N250/ 300H−2SStart the compressor and check for leaks and coolant level Separator tank / Pressure systemAir filter change procedure N250/300H−2S Air filter change procedureAircooled Cooler Cleaning Blower motor Re−GreaseN50/100H N37/75K High Airend Temperature Sensor checking procedure Watercooled Cooler CleaningCoolant Coolers AftercoolerMotor cowl cleaning N75−160 units only Blower / fan Motor Bearing Maintenance Stored unitsDrive Box Filter Removal / Replacement Moisture Separator Check / CleaningNo Loss Drain Trap where fitted Check / Cleaning Coolant Sampling ProcedureFluid and Vibration Monitoring General Faults Fault FindingSymptom Fault Remedy Compressor will not No power supply to packageCheck and modify settings With correct coolant Or not sealing correctlySee above With coolant’Remove blockage, repair or replace damaged Pressure transducer Fault Cause RemedyDrive Faults Fault Cause ActionIndicated on the INTELhYS Controller