Raypak 0090B, 0030B, 0135B manual Replacement Parts List, Raypak, Inc

Page 34

9.Fast-Response Temperature Sensor Module Replacement

a)Shut-off electrical power to the boiler.

b)Remove control cover screws and open control compartment.

c)Disconnect wiring to the board.

d)Carefully pull out the control board from the nylon pin supports.

e)Reverse above procedure to re-install.

10.Fast-Response Temperature Sensor Probe Replacement

a)Shut-off electrical power to the boiler.

b)Shut-off water supply to the boiler and open drain valve to remove water to the sensor probe level.

c)Remove control cover screws and open control compartment.

d)Disconnect wire leads from control board.

e)Remove upper access panel.

f)Remove sensor probe from in/out header.

g)Reverse above procedure to re-install.

11.Circulator Replacement

a)Shut-off electrical power to the boiler.

b)Shut-off water supply and open drain valve to remove water in the piping at the pump level.

CAUTION: To avoid damage to electrical components keep water from getting into the control compartments and gas valve.

c)Disconnect wiring and conduit connections to the pump.

d)Disconnect the bypass tube connections to the inlet flange.

e)Remove the nuts and bolts at the inlet and outlet flanges. Remove old gaskets.

f)Remove the pump.

g)Reverse the above procedure to re-install. Use new gaskets and make sure they are seated properly when tightening the nuts and bolts.

12.2-Stage Controller (Models 90, 135 & 180)

a)Shut-off electrical power to the boiler.

b)Remove control cover screws and open con- trol compartment.

c)The control is factory set at 160°F. To adjust to another setting, use a small screw driver

and turn dial clockwise

to lower the

temperature or counter-clockwise

to

raise the setting.

 

 

d)To replace the stage controller, disconnect the wiring connections.

e)Remove screws (2) holding the staged controller.

f)Remove upper access panel.

g)Remove the wedge or retaining clip holding the sensing bulb in the control well in the in/ out header.

h)Pull out the sensing bulb carefully from the control well.

i)Remove the stage control with capillary from unit.

j)Reverse above procedure to re-install.

6. REPLACEMENT PARTS LIST

NOTE: To supply the correct part it is important that you supply the model number, serial number and type of gas when applicable.

Any part returned for replacement under standard company warranties must be properly tagged with RAYPAK return parts tag, completely filled in with the heater serial number, model number etc., and shipped to Raypak freight prepaid.

If determined defective by Raypak and within war- ranty, the part will be returned in kind or equal substitu- tion, freight collect. Credit will not be issued.

RAYPAK, INC.

2151 Eastman Avenue

Oxnard, CA 93030

34

Image 34
Contents Installation Operating Instructions For Your SafetyContents Specifications and Dimensions General SpecificationsReceiving Equipment Mounting Base Installation ProceduresCode Requirements ClearancerequirementsVenting Connections Fig. #8198.0Common Vents Fig.#Vent Damper Installation LocationD80D General Wiring Diagram Installing the Vent Damper in Horizontal & Vertical VentMounting Vent Damper Operation Vent Damper Position IndicatorSystem Schematic Ladder Diagram Flair DamperConnection Diagram Gaspressure GAS Supply ConnectionsWater Connections & System Piping Piping Diagrams SINGLE-ZONEPIPINGZone Heating with Indirect Domestic HOT Water Supply Multiple Zones with Zone Valves Electrical Wiring Fig.#Wiring Diagram KEY Page Page Wiring Diagram Single-Zone Taco Valve Wiring Diagram System with 3 Zone Pumps Fig. #2223.2e Wiring Diagram Standing Pilot With Low Water Cut-off Device Control BOX Component Locations Models 135 Servicing ProceduresGeneral Location of Controls Sequence of Operation Intermittent Ignition Device IIDSTART-UPPROCEDURES What to do if YOU Smell GASHoneywell Pilot Robertshaw Pilot For Automatic Ignition ModelsSHUT-DOWNPROCEDURE To Turn OFF GAS to BoilerFor Automatic Ignition Systems Safe SHUT-DOWN Tests Limit Action Inspection Procedures BurnersInspectionprocedures Flame FailureRaypak Tube Cleaning KIT RepairproceduresHeat Exchanger RE-ASSEMBLY Combustion Chamber RemovalTroubleshooting Guide Important NoticePiping ADJUSTMENT/REPLACEMENTOF Components Replacement Parts List RAYPAK, INCPage Page Page Limited Parts Warranty