Raypak 0090B Safe SHUT-DOWN Tests Limit Action, Flame Failure, Inspection Procedures Burners

Page 28

SAFE SHUT-DOWN TESTS

LIMIT ACTION

With the burner operating, lower the high limit setting to simulate an overheated boiler. Normal shut- down should occur. Restore the normal limit setting, and the burner should restart.

FLAME FAILURE

With burner operating, close the manual fuel valves to simulate a flame failure. System should lock out after safety switch timing (15 seconds). After the safety switch has cooled, open the manual valves (relight standing pilots) and reset the safety switch; the burner should restart.

INSPECTION PROCEDURES

BURNERS

Clean main burners and air louvers of dust, lint and debris. Keep boiler area clear and free from combustibles and flammable liquids. Do not obstruct the flow of combustion and ventilation air. Make visual check of burner and pilot flame. Yellow flame indicates clogging of air openings. Lifting or blowing flame indicates high gas pressure. Low flame indicates low gas pressure.

Fig. #8964

PILOT BURNER FLAME (STANDING PILOT UNITS)

INSPECTIONPROCEDURES

To be performed the first and third month after initial start up and then on an annual basis. If problems are found, refer to Troubleshooting Guide for additional direc- tions.

1.Remove top of boiler and inspect heat exchanger for soot and examine venting system.

2.Remove rear header and inspect for scale depos- its.

*3. Inspect pilot and main burner flame and firing rate.

*4. Inspect and operate all controls and gas valve.

*5. Visually inspect system for water leaks.

*6. Inspect oil pump motor and bearing assembly, if oil cups are provided.

7.Check flow switch paddle.

8.Clean room air intake openings to ensure adequate flow of combustion and ventilation air.

9.Keep boiler area clear and free from combustible materials, gasoline, and other flammable vapors and liquids.

*Should be checked monthly. (Takes approximately 15 minutes).

Fig. #8144

MAIN BURNER FLAME

NOTE: Modulating burner flame varies in height from approximately 1/4" at low fire to approximately 4" in high fire.

28

Image 28
Contents Installation Operating Instructions For Your SafetyContents Specifications and Dimensions General SpecificationsReceiving Equipment Installation Procedures Code RequirementsMounting Base ClearancerequirementsVenting Connections Fig. #8198.0Common Vents Fig.#Vent Damper Installation LocationD80D General Wiring Diagram Installing the Vent Damper in Horizontal & Vertical VentMounting Vent Damper Position Indicator System Schematic Ladder DiagramVent Damper Operation Flair DamperConnection Diagram Gaspressure GAS Supply ConnectionsWater Connections & System Piping Piping Diagrams SINGLE-ZONEPIPINGZone Heating with Indirect Domestic HOT Water Supply Multiple Zones with Zone Valves Electrical Wiring Fig.#Wiring Diagram KEY Page Page Wiring Diagram Single-Zone Taco Valve Wiring Diagram System with 3 Zone Pumps Fig. #2223.2e Wiring Diagram Standing Pilot With Low Water Cut-off Device Servicing Procedures General Location of ControlsControl BOX Component Locations Models 135 Sequence of Operation Intermittent Ignition Device IIDSTART-UPPROCEDURES What to do if YOU Smell GASHoneywell Pilot Robertshaw Pilot For Automatic Ignition ModelsSHUT-DOWNPROCEDURE To Turn OFF GAS to BoilerFor Automatic Ignition Systems Inspection Procedures Burners InspectionproceduresSafe SHUT-DOWN Tests Limit Action Flame FailureRaypak Tube Cleaning KIT RepairproceduresHeat Exchanger RE-ASSEMBLY Combustion Chamber RemovalTroubleshooting Guide Important NoticePiping ADJUSTMENT/REPLACEMENTOF Components Replacement Parts List RAYPAK, INCPage Page Page Limited Parts Warranty