Slant/Fin J-390 installation instructions Boiler Location, Boiler Foundation, Safety

Page 4

4

Jaguar Model J-390

INSTALLATION REQUIREMENTS

The installation must conform to the requirements of the authority having jurisdiction or, in the absence of such requirements, to the National Fuel Gas Code, ANSI Z223.1- latest edition.

This installation must also conform to the additional require- ments in this Slant/Fin Instruction Book.

BOILER LOCATION

Provide a level, solid foundation for the boiler. Location should be as near as possible to chimney or outside wall so that the flue pipe from boiler is short and direct. (See para- graph heading “Vent Termination Location and Clearance” on page 8.) The location should also be such that all boiler components are protected from water (dripping, spraying, rain, etc.) during appliance operation and service (circulator replacement, control replacement, etc.).

BOILER FOUNDATION

A.Provide a solid, level foundation, capable of supporting the weight of the boiler filled with water, and extending at least 2" past the jacket on all sides. See dimensions of boilers, page 2.

B.Boiler can be installed on both combustible and non-combustible floors, but must NOT be installed on or above carpeting.

C.If boiler is to be located over buried conduit containing electric wires or telephone cables, consult local codes or the National Board of Fire Underwriters for specific requirements.

* 2" FOR ENCLOSED

MINIMUM CLEARANCES FROM COMBUSTIBLE CONSTRUCTIONS

A.Minimum clearances to the exterior surfaces of the boiler shall be as follows:

MINIMUM ALCOVE AND CLOSET CLEARANCE

 

For Combustible

Recommended

Surface

Construction

for Service

Front

0"

24"

Rear

0"

6"

Left Side

0"

0"

Right Side

0"

0"

Top

4"

6"

Flue Connector:

 

 

Enclosed —

2"

6"

Uninclosed —

1"

6"

 

 

 

B.Provide accessibility clearance of 8" on sides requiring servicing and 18" on sides used for passage.

C.All minimum clearances shown above must be met. This may result in increased values of some minimum clear- ances in order to maintain the minimum clearances of others.

D.Clearance from hot water pipes shall be 1 inch**.

**At points where hot water pipes emerge from a floor, wall or ceiling, the clearance at the opening through the finished floor boards or wall or ceiling boards may be not less than 1/2 inch. Each such opening shall be covered with a plate of uncombustible material.

SAFETY

KEEP THE BOILER AREA CLEAR AND FREE FROM COMBUSTIBLE MATERIALS, GASOLINE AND OTHER FLAMMABLE VAPORS AND LIQUIDS.

Figure 3. Jaguar boiler min. clearances for combustible construction.

Image 4
Contents Installation and Operating Instructions Ratings and Dimensions Jaguar J-390 BoilerLocation and Identification of Parts Location and identification of partsSafety Boiler LocationBoiler Foundation Minimum Clearances from Combustible ConstructionsNON-DIRECT Vent Installation Direct Vent InstallationContamination Prevention Products to AvoidFlue GAS Venting Requirements Vent and AIR Intake MaterialsPVC/CPVC Pipe General Assembly Method Vent and AIR Intake RestrictionsVenting Installation Sidewall Venting NON-DIRECT VentVent Termination Location and Clearances NON-DIRECT Vent Vertical VentingJaguar J-390 NON-DIRECT VENT, Sidewall Venting 10 MAXJaguar J-390 NON-DIRECT VENT, Venting Through a Roof FT. MINFT. MIN Jaguar J-390 Direct VENT, Sidewall Venting Thick WallDIA PVC/CPVC Pipe for Vent Combustion Screw Jaguar Model J-390 Direct Vent Venting and AIR Intake Through a Roof FT. MINVenting and AIR Intake System Regular Inspection Condensate Removal SystemCommonwealth of Massachusetts Special Requirement GAS PipingElectrical Wiring Space Heating ThermostatsDomestic HOT Water Tank Thermostat Outdoor AIR Sensor101112 Boiler Control 120V 3 4 5 6 7 3 4 5 6 7 Thermostat Water Piping Water Outlet Piping Tank Piping JaguarFeet w.c Zoning with circulators Zoning with zone valves Piping a heating-cooling system to the boiler and a chiller View and Changing Temperatures Viewing and changing system settingOperating Instructions Filling and Venting Water Systems Before Firing BOILER, make these checksJaguar Boiler Display Board Boiler Operation StatusViewing and Changing Temperatures If outdoor sensor is usedBoiler model selection, value is 5 for model J-390 Water Safety Information III. Initial StartInstructions To Turn OFF GAS to ApplianceJaguar Model J-390 Sequence of Operation Gas valve adjustment IV. Check Combustion and Fuel Input RateSafety Check Control Safety Shutdown testVI. Diagnostic Error Codes Check for gas leaks19, 42 Going to the sensor, or replace the sensor. If no sen Care and Maintenance General MaintenanceIII. Cleaning If Replacement Parts are NeededGeneral Troubleshooting Guide for Service Personnel Jaguar Model J-390 SLANT/FIN CORPORATION, Greenvale, N.Y Phone 516