Slant/Fin installation instructions Jaguar J-390 NON-DIRECT VENT, Sidewall Venting, 10 MAX

Page 9

Jaguar Model J-390

9

JAGUAR J-390 NON-DIRECT VENT, SIDEWALL VENTING

All joints must be liquid and pressure tight. Use 4” dia. PVC/CPVC schedule 40 pipe or U/L listed single wall 4" dia.

 

AL29-4C S.S.*. venting materials (See page 7).

 

SLOPE UP 1/4 IN.

6" MIN.

 

PER FOOT MIN.

10" MAX.

 

FROM BOILER TO

 

 

VENT TERMINATION

 

4 IN. DIA.

 

 

PVC/CVPC

 

 

PIPE FOR

TERMINATION 90 ELBOW

 

VENT

 

WITH SCREEN

 

 

 

90 ELBOW

 

 

AIR INTAKE

 

 

(DO NOT BL0CK)

 

 

 

A U/L LISTED FLASHING

 

 

AND SEALING BOOT MUST

 

 

BE USED ON COMBUSTIBLE

12" MIN

 

WALLS.

 

 

 

SNOW LINE

 

 

(SEE DEFINITION)

 

OUTSIDE WALL

 

Figure 6. Non-direct vent, side wall venting - utilizing PVC/CPVC pipe for venting.

SLOPE UP 1/4 IN.

PER FOOT MIN. FROM BOILER TO VENT TERMINATION

6" MIN 10" MAX

4 INCH. DIA.

 

STAINLESS

 

STEEL VENTING

OUTSIDE VENT TERMINATION

MATERIAL FOR

ELBOW WITH SCREEN

VENT

 

STANDARD

 

90 ELBOW

 

AIR INTAKE

 

(DO NOT BL0CK)

WALL THIMBLE MUST BE USED

 

ON COMBUSTIBLE WALLS

 

12" MIN

 

SNOW LINE

 

(SEE DEFINITION)

 

OUTSIDE WALL

Figure 7. Non-direct vent, side wall venting - utilizing stainless steel vent materials for venting.

**Definition of Snow Line: Knowledge of local conditions will reveal the maximum height that repeated snowfalls accumulate to. The height should be used as the SNOW LINE.

* AL 29-4C IS A REGISTERED TRADEMARK OF ALLEGHENY LUDLUM CORP.

Image 9
Contents Installation and Operating Instructions Jaguar J-390 Boiler Ratings and DimensionsLocation and identification of parts Location and Identification of PartsBoiler Location SafetyBoiler Foundation Minimum Clearances from Combustible ConstructionsDirect Vent Installation NON-DIRECT Vent InstallationContamination Prevention Products to AvoidVent and AIR Intake Materials Flue GAS Venting RequirementsVent and AIR Intake Restrictions PVC/CPVC Pipe General Assembly MethodSidewall Venting NON-DIRECT Vent Venting InstallationVent Termination Location and Clearances NON-DIRECT Vent Vertical Venting10 MAX Jaguar J-390 NON-DIRECT VENT, Sidewall VentingFT. MIN Jaguar J-390 NON-DIRECT VENT, Venting Through a RoofFT. MIN Thick Wall Jaguar J-390 Direct VENT, Sidewall VentingDIA PVC/CPVC Pipe for Vent Combustion Screw Jaguar Model J-390 FT. MIN Direct Vent Venting and AIR Intake Through a RoofCondensate Removal System Venting and AIR Intake System Regular InspectionCommonwealth of Massachusetts Special Requirement GAS PipingSpace Heating Thermostats Electrical WiringDomestic HOT Water Tank Thermostat Outdoor AIR Sensor101112 Boiler Control 120V 3 4 5 6 7 3 4 5 6 7 Thermostat Water Piping Water Outlet Piping Jaguar Tank PipingFeet w.c Zoning with circulators Zoning with zone valves Piping a heating-cooling system to the boiler and a chiller Viewing and changing system setting View and Changing TemperaturesOperating Instructions Filling and Venting Water Systems Before Firing BOILER, make these checksBoiler Operation Status Jaguar Boiler Display BoardIf outdoor sensor is used Viewing and Changing TemperaturesBoiler model selection, value is 5 for model J-390 Water III. Initial Start Safety InformationInstructions To Turn OFF GAS to ApplianceJaguar Model J-390 Sequence of Operation IV. Check Combustion and Fuel Input Rate Gas valve adjustmentControl Safety Shutdown test Safety CheckVI. Diagnostic Error Codes Check for gas leaks19, 42 Going to the sensor, or replace the sensor. If no sen General Maintenance Care and MaintenanceIII. Cleaning If Replacement Parts are NeededGeneral Troubleshooting Guide for Service Personnel Jaguar Model J-390 SLANT/FIN CORPORATION, Greenvale, N.Y Phone 516