VENTING INSTALLATION

HBDV7 Series Direct Vent Gas Fireplace

Vertical Sidewall Installation - Twist Lock Pipe

Step 1

Locate vent opening on the wall. It may be necessary to first position the fireplace and measure to obtain hole lo- cation. Depending on whether the wall is combustible or noncombustible, cut opening to size. Figure 28 (For com- bustible walls first frame in opening.)

NOTE: When using flex vent, the opening will have to be measured according to the 1/2” (13 mm) rise in 12” (305 mm) vent run.

Combustible Walls: Cut a 9B\,”H x 9B\,”W (244 x 244 mm) hole through the exterior wall and frame as shown. Figure 28

Noncombustible Walls: Hole opening must be 7Z\x” (191 mm) in diameter.

Vent Opening for Combustible Walls

9B\,

(244 mm) Min.

9B\,

(244 mm)

Min.

Fireplace Hearth

Framing Detail

Opening for Noncombustible Wall

 

7Z\x

 

 

 

 

 

 

 

(190 mm)

 

 

 

 

 

 

 

 

 

 

FP2293

 

 

 

 

 

 

 

Figure 28 -

 

Fireplace Hearth

 

 

Locate vent opening on wall.

Step 2

Secure firestop to the inside frame, center in the 9B\," x 9B\," vent opening.

Step 3

Place fireplace into position. Measure the vertical height

(X)required from the base of the flue collars to the center of the wall opening. Figure 29

Step 4

Using appropriate length of pipe section(s) attach to fire- place with three (3) screws. Follow with the installation of the inner and outer elbow, again secure joints with three

(3) sheet metal screws.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

X

 

 

 

 

 

 

 

 

 

 

 

 

 

X

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

FP1181

Figure 29 -

Vertical Height Requirements

Step 5

Measure the horizontal length requirement including a 2” (51 mm) overlap, i.e. from the elbow to the outside wall face plus 2” (51 mm) (or the distance required if installing a second 90° elbow). Figure 30

Always install horizontal venting on a level plane.

Step 6

Use appropriate length of pipe sections - telescopic or fixed - and install. The sections which go through the wall are packaged with the starter kit, and can be cut to suit if necessary.

Sealing vent pipe and firestop gaps with high tem- perature sealant will restrict cold air being drawn in around fireplace.

X

X

Figure 30 -

FP1182

Horizontal Length Requirements

 

54D8000

19

Image 19
Contents HBDV7 Series Direct Vent Gas Fireplace Check Gas Pressure Signature Command System Pre-Installation InformationMassachusetts Residents Only Installer Important Safety InformationOwner Code Approval Please Read the Following CarefullyNever connect unit to private non Known as wellhead gasHigh Elevations Product SpecificationsHBDV300 HBDV400 Framing DimensionsCold Climate Insulation PRE-INSTALLATION InformationFirebox framing Fireplace LocationOutlet grilles louvers. This may create a Clearances to combustiblesMantel Clearances Never obstruct or modify the air inlet orFinishing Material Secure Fireplace to Floor or FramingOptional TOP Vent Application Optional top vent applicationInstallation precautions Venting Installation InformationGeneral Venting General Venting Information Termination Location Canadian Installations1 US Installations2Canadian Installations USA InstallationsTermination Clearances Twist Lock Pipes How to Use the Vent GraphRefer to Page 21 for requirements for snorkels 1219 mm Vent InstallationRear Wall Vent Application Rear Wall Vent Installation Twist Lock PipeStep Vent configurations apply and must be strictly adhered to Rear Wall Vent Installations Flex Vent PipeTop vent Sidewall Application + B = 17 Max Vertical Sidewall Installation Twist Lock Pipe Venting InstallationAlways install horizontal venting on a level plane Install the 4 flex then 7 flex to the termination Vertical Sidewall installation flex vent pipeVertical THROUGH-THE-ROOF APPLICA- Tion Below Grade InstallationsDo not back fill around snorkel Vertical THROUGH-THE-ROOF Installation Roof Flashing Check gas type Install gas piping to fireplace / burner system locationNatural Gas Fireplace InstallationPropane/LP Leaks Millivolt Check GAS Pressure and Electrical installationElectrical Wiring Do not use open flame to check for gasOptional DC Remote Systems Electrical InstallationRemote Wall mounted Switch Remote Wall SwitchInitial lighting What to do if YOU Smell GASNever use an open flame to check for gas leak Flame Approved leak testing methodOperating Instructions Millivolt Never check for gas leak with openLighting the burner Main burner switchPilot position Or performing service. All wiring shall be Optional Accessory RequirementsElectrician. Main power must be off when Connecting to main electrical power supplyCommand Center Wall Installation Junction BOX WiringWall Switch Installation Nected together if a wall switch is not Being used Blotsc Signature Command Blower Blot Automatic Thermostat Blower Optional FAN Blower SystemsFK-12 Manual Blower On next Command Center Operating Instructions Signature CommandBattery Installation FeaturesCommand Center Function Operation Default Setting Key Combinations for System SettingsFunction Operation Command Center OperationsSelf Diagnostics Chart FUNCTIONS/OPERATIONGlass Removal Brick installationGlass Frame Removal Hazard Placement of Lava ROCK, Rock Wool and LogsDo not sprinkle the lava rock or ember Potential sooting, glass breakage and a fireFinal Installation Left Front Log #6 Installing Universal Andirons Burner, Pilot and Control Compart- ment Rock wool Vent SysteMGlass Door LogsStanding Pilot Ignition Symptom Possible Cause ActionTroubleshooting Signature Command System Firebox Components Replacement PartsDescription Qty Firebox componentsStanding Pilot Millivolt Control Fuel Conversion Kits Natural Gas to LP AccessoriesLP to Natural Gas Signature Command System HBDV300NSC7 HBDV300PSC7 HBDV400NSC7 HBDV400PSC7 Logs Replacement PartsDescription Qty Description Model Number Vertical Venting7TBLSCTK Horizontal VentingHBDV7 Series Direct Vent Gas Fireplace HBDV7 Series Direct Vent Gas Fireplace Carbon Monoxide Detector Requirements If Warranty Service is Needed Lifetime WarrantyFive Year Warranty Basic WarrantyModel EnerGuide Ratings Fireplace Efficiency % Mhsc