Baxi Potterton G.C.No 47 393 21 manual Installation, Unpacking & Initial Preparation, Flushing

Page 28

Fig. 39

Fig. 40

145mm

For Side Flue Exit

Fig. 41

Flushing Tube

Wall Plate

Central Heating Return

Fig. 42

 

10.0Installation

10.1Unpacking & Initial Preparation

The gas supply, gas type and pressure must be checked for suitability before connection (see Section 7.4).

NOTE: a small amount of water may drain from the boiler in the upright position.

1.Remove staples, open flaps and remove the cardboard sheet. Remove the polystyrene side pieces and literature. Two people can then lift out the boiler (Figs. 39 & 40)

2.After considering the site requirements

(see Section 7.0) position the fixing template on the wall ensuring it is level both horizontally and vertically.

3.Mark the position of the two most suitable fixing slots for the wall plate and boiler lower fixing holes. It is preferable to use the vertical fixing slots.

4.Mark the position of the centre of the flue hole (rear exit). For side flue exit, mark as shown (Fig. 41).

5.If required, mark the position of the gas and water pipes. Remove the template.

6.Cut the hole for the flue (minimum diameter 116mm).

7.Drill the wall as previously marked to accept the wall plugs supplied. Secure the wall plate using the fixing screws.

8.Using a spirit level ensure that the plate is level before finally tightening the screws.

9.Connect the gas and water pipes to the valves on the wall plate using the copper tails supplied. Ensure that the sealing washers are fitted between the connections.

10.2Flushing

1.Connect a tube to the central heating flow or return pipe (Fig. 42).

2.Flush thoroughly (see System Details, Section 6.1).

28© Baxi Heating UK Ltd 2011

Image 28
Contents Installation & Service Instructions 0086 Installer Notification Guidelines Scheme Members onlyLegislation Important Installation, Commissioning, Service & RepairCodes of Practice refer to the most recent version Safe Manual Handling GeneralPreparation TechniqueContents Introduction Contents of PackDescription General Layout LayoutAppliance Operation Frost Protection ModePump Protection Technical Data Promax Combi 24, 28Dimensions and Fixings OrientationTap Rail 32.5 mm Condensate Drain 65 mmSystem Details InformationCentral Heating Circuit BypassExpansion Vessel Central Heating only System Filling and Pressurising FigPressure Relief Valve Fig Showers Domestic Hot Water Circuit FigHard Water Areas Location Site RequirementsAt Least 1.5 7.2 Clearances Figs Site Requirement Ventilation of CompartmentsGas Supply Electrical SupplyCondensate Drain Flue Flue terminal guardEach fitting to aid assembly Flue OptionsHorizontal Flue Systems Horizontal FluesVertical Flues Twin & Vertical Flue Systems120mm Min ApartKey Accessory Size Code No Flue AccessoriesTelescopic Internal Flue Kit Twin Flue Connection Twin Flue Duct AdaptorAir Duct Connection Flue Duct Connection Boiler Adaptor Flue Dimensions For Roof TerminalsFlue Trim Terminal Guard FigPlume Displacement Kit Fig Plume DisplacementMetres Ring Adaptor 28/33 Determining Permissible Lengths Example 5121368General Fitting Notes 30mmElbow to allow the flue to be installed as shown 60Ø extension piece. It must be secured using twoUsing a suitable bit e.g mm, drill through Extension and outlet. Secure using two of the screwsInstallation Unpacking & Initial PreparationFlushing After considering the site requirementsFitting The Boiler Fitting the Pressure Relief Discharge Pipe FigCondensate Drain see section Tighten all the connectionsFitting The Flue Wall Thickness WasteFlue Elbow Ensure Elbow is fully Engaged into Boiler25mm Extension Cut End Inner Flue Support BracketEnsure Extension is fully engaged into Boiler Adaptor Preliminary Electrical Checks Making The Electrical ConnectionsTerminal Block Cover Cable Clamp Commissioning Commissioning the BoilerPressure Completion CompletionCase Front Panel Facia Panel Servicing 13 .1 Annual ServicingAnnual Servicing Inspection Case Front Panel Facia Panel Securing ScrewsBurner Sensing Electrode 10 ±1Viewing Window Igniter Fig Changing ComponentsSpark and Sensing Electrodes Fig Fan Fig Venturi FigInjector Fig Gasket Venturi Injector Cover Gas Inlet Pipe Fan CollectorInsulation Fig Burner FigBurner Gasket Extension Piece Central Heating Temperature Sensor NTC Fig Safety Thermostat FigDHW Temperature Sensor NTC Fig Flue/Heat Exchanger Thermostat Sensor FigPump Complete Fig Pump Head Only FigAutomatic Air Vent Fig Pressure Gauge Figs Hall Effect Sensor FigDiverter Valve Motor Unit & Assembly Fig Plate Heat Exchanger FigSelector Switch Fig 14.22 P.C.B. FigGas Valve Fig Throttle Adjustment ScrewExpansion Vessel Fig Setting the Gas Valve Setting the Gas Valve CO2 checkFlue Adaptor Test Point Plug Analyser Probe ThrottleIllustrated Wiring Diagram ElectricalShort Parts List Short Parts List306 302Initial Fault Finding Checks Fault FindingError Codes Error 133 flashing Go to section ‘A’ Turn the selector switch toReset position for 5 seconds Pump runsTurn selector switch to Error 133 flashing Go to section ‘I’Turn Domestic Hot Water Open DHW tap fullyPCB X3 connector terminals 3 Switch terminalFan jammed or faulty winding Replace PCB Replace waterCheck wiring Viewing Window Replace sensor or PCB E28Gas at burner Replace gas valveReplace PCB Is there 230V at Replace safety thermostatReplace sensor Page Page Condensing Boilers only Service Record Brooks House, Coventry Road, Warwick. CV34 4LL