APC UCCS Temperature Control specifications Quality Assurance, Ownership of Proprietary Material

Page 11

E. The Contractor shall optimize all control software and tune all control loops to assure acceptable operating and space conditions and peak energy efficiency. This shall include changes needed to optimize operation of the systems even if not explicitly described in Control Strategies.

F. The Contractor shall include the extended warranty for upgrades of ethernet controllers installed in the building for the warranty year.

G.At the end of the warranty period, the Contractor shall supply updated copies of the latest versions of all project record documentation as described in Paragraph 1.08, Project Record Documents. This includes final updated drawings, software documentation, and electronic media backups that include all changes that have been made to the system during the

warranty period.

H. Coordinate with the UCCS HVAC Shop in

advance before connecting new DDC control system to campus network.

I. Once the building DDC is connected to the network, the Contractor shall notify a representative of the UCCS HVAC Shop before and after performing any work on the DDC components, and report any changes made.

J. During the warranty period, University personnel shall make a reasonable effort to determine if a problem is due to the control system or some other source not the respon- sibility of the Controls Contractor, before requesting warranty service. However, if the Controls Contractor is called out and determines that the problem is not due to the controls system or other building components, the Contractor shall not charge the University for a service call if it is determined that the source of the problem is not his responsibility.

1.11QUALITY ASSURANCE

A. This installation shall not be used as a test site for any new products unless explicitly approved by the Owner's representative in writing. This requirement is not intended to restrict the Contractor to the use of outdated equipment.

B. All products used in this installation shall be new and currently under manufacture. Spare parts shall be available for at least ten (10) years after completion of this contract.

C. All DDC components shall be compatible with the rest of the DDC network at the beginning of the warranty period.

1.12OWNERSHIP OF PROPRIETARY MATERIAL

A. All project developed hardware and software shall become the property of the Owner. These include but are not limited to:

1.Project graphic images,

2.Record drawings,

JANUARY 2008

UCCS STANDARDS

15950-11

Image 11
Contents Uccs Temperature Control Specifiers Guide Section Controls Part 1 General Special Conditions Work Included Submittal Data and Shop Drawings Drawings and SpecificationsDefinitions 15950-6 15950-7 Project Record Documents Demonstration and Training Warranty Ownership of Proprietary Material Quality AssurancePart 2 Products Manufacturers 15950-13 15950-14 Duct-mounted Uccs to add preferred manufacturer here 15950-16 Control Valves AIR Tubing and Control Wiring15950-18 Local Control Panels Compressed AIR Supply Pneumatic Actuators and Positioners Pneumatic 15950-22 15950-23 15950-24 Transmitters Solid State SOLID-STATE Sensing Devices15950-26 Auxiliary Devices Electric Actuators Electric Part 3 Execution CONTROL-AIR Piping Safety ControlsControl Piping Liquids Control Wiring SCX 920 LCX 810, TCX 850, LCX 800I ALL Infinity Controllers NET ControllersInstallation and Setup Requirements 15950-34 Control Device Locations Identification Control PanelsProtection CleanupTesting 15950-38 Control Execution General Workstation Programming 15950-41 END of Section DDC Software