Page 40

G.System logs, trend logs, and event-initiated logs shall be set up to provide historical and real-time monitoring of system operation. Logs shall be grouped by equipment.

H.Safety Shutdowns - Boilers and Chiller: Boilers and/or chiller will be provided with all required safety controls as specified in Division 15. Safety trip shall shut down respective boiler or chiller directly and shall be annunciated at the Central Work Station.

I.Safety Shutdowns - General: All safety shutdowns of electrical equipment shall be hard- wired. All shutdowns shall occur directly through interconnection of contacts on the safety device with the controlling circuit of the electrical equipment. Safety shutdowns through software are not acceptable. Interposing relays may be used only with prior approval of the Engineer and Owner's Representative when no alternative exists.

J.This Contractor shall notify the University two weeks in advance of when connection to the BAS network will be beneficial to the system so the work can be scheduled.

3.13WORKSTATION PROGRAMMING

A. The University has multiple workstations networked across the campus. The main file server is located in the Facilities HVAC office in the Stadium Building. All graphics, alarms, trend logs, and schedules shall be accessible from any workstation and be fully integrated with existing menus.

B.Graphics:

1.The system shall be programmed by the Controls Contractor to provide a color graphic for:

a.Opening screen graphic showing the building, campus, facility, etc.

b.Each HVAC air and water system monitored or controlled

c.Each floor and zone controlled (floor plan) - both HVAC and smoke detectors where applicable

d.Each VAV box with DDC controls

e.Each electrical subsystem monitored or controlled

f.Each prime mover subsystem (boilers, chillers, heat exchangers, pumps, towers, and distribution system)

g.Each time-scheduling program

h.Utility consumption and outdoor condition logs

i.Fuel oil and generator systems

JANUARY 2008

UCCS STANDARDS

15950-40

Image 40
Contents Uccs Temperature Control Specifiers Guide Section Controls Part 1 General Special Conditions Work Included Definitions Drawings and SpecificationsSubmittal Data and Shop Drawings 15950-6 15950-7 Project Record Documents Demonstration and Training Warranty Quality Assurance Ownership of Proprietary MaterialPart 2 Products Manufacturers 15950-13 15950-14 Duct-mounted Uccs to add preferred manufacturer here 15950-16 AIR Tubing and Control Wiring Control Valves15950-18 Local Control Panels Compressed AIR Supply Pneumatic Actuators and Positioners Pneumatic 15950-22 15950-23 15950-24 SOLID-STATE Sensing Devices Transmitters Solid State15950-26 Auxiliary Devices Electric Actuators Electric Safety Controls Part 3 Execution CONTROL-AIR PipingControl Piping Liquids Control Wiring NET Controllers SCX 920 LCX 810, TCX 850, LCX 800I ALL Infinity ControllersInstallation and Setup Requirements 15950-34 Control Device Locations Control Panels IdentificationTesting CleanupProtection 15950-38 Control Execution General Workstation Programming 15950-41 DDC Software END of Section