6.When connecting DDC controllers, terminating of inputs and outputs shall be color coded as follows :

120VAC shall be black = hot, white = neutral, green = ground 24VAC shall be (+) black with white tracer, (-) white with black tracer 24VDC shall be (+) red with black tracer, (-) black with red tracer

All pneumatic tubing shall be labeled within 2" of termination with a descriptive identifier.

7.All metal and plastic engraved labels shall be secured with chains, nylon tie-wraps, or rivets. Permanent adhesive is acceptable only when mechanical fasteners would dam- age the labeled equipment.

8.All switches, relays, and panel components shall be labeled.

9.Labels shall not be mounted on removable surfaces, such as cable tray covers.

3.09PROTECTION

A.The Contractor shall protect all work and material from damage by his work or workmen, and shall be liable for all damage thus caused.

B.The Contractor shall be responsible for work and equipment until finally inspected, tested, and accepted. He shall protect work against theft, injury, or damage; and shall carefully store material and equipment received on site which is not immediately installed. He shall close open ends of work with temporary covers or plugs during storage and construction to prevent entry of foreign objects.

3.10 CLEANUP

A.At the completion of work, all equipment on the project shall be checked and thoroughly cleaned including under equipment and any and all other areas around or in equipment provided under this section. Clean exposed surfaces of all equipment and panels of all grease, plaster, or other foreign material. Remove all stick-on labels and clean surfaces.

B.At the completion of the work, remove from the building, the premises, and surrounding streets, alleys, etc., all rubbish and debris resulting from this project, and leave all equipment spaces clean and ready for use.

C.At the completion of work, all equipment furnished under this contract shall be checked for paint damage, and any factory finished paint that has been damaged shall be repaired to match the adjacent areas. Any metal cabinet, jacket, or enclosure that has been deformed shall be replaced with new material and repainted to match the adjacent areas.

3.11TESTING

A.Prior to substantial completion, the control system shall undergo a series of tests to verify operation and compliance with this specification. These tests shall occur after the Con-

tractor has completed the installation, started up the system, and performed his own per-

JANUARY 2008

UCCS STANDARDS

15950-37

Image 37
Contents Uccs Temperature Control Specifiers Guide Section Controls Part 1 General Special Conditions Work Included Definitions Drawings and SpecificationsSubmittal Data and Shop Drawings 15950-6 15950-7 Project Record Documents Demonstration and Training Warranty Ownership of Proprietary Material Quality AssurancePart 2 Products Manufacturers 15950-13 15950-14 Duct-mounted Uccs to add preferred manufacturer here 15950-16 Control Valves AIR Tubing and Control Wiring15950-18 Local Control Panels Compressed AIR Supply Pneumatic Actuators and Positioners Pneumatic 15950-22 15950-23 15950-24 Transmitters Solid State SOLID-STATE Sensing Devices15950-26 Auxiliary Devices Electric Actuators Electric Part 3 Execution CONTROL-AIR Piping Safety ControlsControl Piping Liquids Control Wiring SCX 920 LCX 810, TCX 850, LCX 800I ALL Infinity Controllers NET ControllersInstallation and Setup Requirements 15950-34 Control Device Locations Identification Control PanelsTesting CleanupProtection 15950-38 Control Execution General Workstation Programming 15950-41 END of Section DDC Software