APC UCCS Temperature Control specifications 15950-7

Page 7

c.Panel software name and serial number

d.Type of controller: The network diagram shall depict the actual connection sequence of the devices, including distances between devices, type of wire used and serial number of controller.

2.The second drawing in the control package shall consist of actual installation details, a valve schedule, and a damper schedule. The valve schedule shall have entries for: Valve tag, system served, quantity type (3w, 2w), GPM, actual CV, actual pressure drop, size, close off rating, spring range, part number, and manufacturer. The damper schedule shall have entries for: Damper tag, system served, quantity, type (PB, OB), CFM, size, actual pressure drop, quantity of actuators, spring range, damper model number, and, and actuator model number.

3.Subsequent drawings shall depict complete systems (air handler, chiller, boiler, etc.). The drawing shall show the system schematic, all wiring of the DDC controller, all wiring of field devices, starters, and connections to equipment. Each drawing shall have a bill of materials and a sequence of operation.

4.Floor plans shall depict equipment location, sensor, and panel locations. The duct and space static pressure monitor points shall be shown.

D.Submittal data and control drawings for all equipment and systems shall be submitted (per Section 01300) to the Architect/Engineer for review prior to ordering or fabrication of the equipment. The following information shall be included in these submittals:

1.30 Days or Less After Notice to Proceed:

a. Control valve and damper schedules which include size, Cv (valves), closeoff pressure rating (valves), [at 0 psi for N.C., two-way valves; at 20 psi for N.O., two-way valves; and at 0 psi between ports A and B for three-way valves], gpm or cfm, spring range of the actuator, quantity of actuators (dampers), and actual pressure drop for each item.

b.Technical specification data sheets of each system component and device which includes all data needed to show compliance with this specification.

2.60 Days or Less After Notice to Proceed:

a. Control drawings with detailed piping and wiring diagrams; system schematics with controlled/monitored device locations; and connections to all enclosures, panels, and controllers, including a bill of material for all systems. Ladder-type electrical schematic diagrams shall be provided for all interlock wiring with magnetic starters, control relays, safety devices, etc.

JANUARY 2008

UCCS STANDARDS

15950-7

Image 7
Contents Uccs Temperature Control Specifiers Guide Section Controls Part 1 General Special Conditions Work Included Definitions Drawings and SpecificationsSubmittal Data and Shop Drawings 15950-6 15950-7 Project Record Documents Demonstration and Training Warranty Ownership of Proprietary Material Quality AssurancePart 2 Products Manufacturers 15950-13 15950-14 Duct-mounted Uccs to add preferred manufacturer here 15950-16 Control Valves AIR Tubing and Control Wiring15950-18 Local Control Panels Compressed AIR Supply Pneumatic Actuators and Positioners Pneumatic 15950-22 15950-23 15950-24 Transmitters Solid State SOLID-STATE Sensing Devices15950-26 Auxiliary Devices Electric Actuators Electric Part 3 Execution CONTROL-AIR Piping Safety ControlsControl Piping Liquids Control Wiring SCX 920 LCX 810, TCX 850, LCX 800I ALL Infinity Controllers NET ControllersInstallation and Setup Requirements 15950-34 Control Device Locations Identification Control PanelsTesting CleanupProtection 15950-38 Control Execution General Workstation Programming 15950-41 END of Section DDC Software