APC UCCS Temperature Control specifications Warranty

Page 10

two- to four-hour sessions over the life of the warranty period. All instructional material shall be available to each employee at each training session up to a maximum of ten (10)

individuals.

F. All demonstration and training sessions shall be coordinated with the University HVAC supervisor.

1.10 WARRANTY

A. The warranty period shall begin as authorized by the Owner's representative in writing. Authorization will not be given before the following conditions are met. Under no condi- tions will the Controls Warranty begin before the starting date of the General Warranty for

the overall project.

1.Completion of the tests required in Paragraph 3.09 and correction of all problems discovered during the testing process.

2.Completion of all punch list items that are the direct responsibility of the Controls Contractor.

3.Conduction of a preliminary training session for personnel of the HVAC Shop of the Department of Facilities Management. The training shall consist of an orientation session at the job site to familiarize the personnel with the location and type of controlled equipment and controls on the project, a discussion of the control sequences, and a review of the control drawings. A copy of the as-built control drawings shall be provided to the HVAC Shop at this time as well. Other, more detailed, training sessions (such as for review of the control programs) may be held at a later date during the warranty period

4.Completion and distribution of the as-built control drawings, including correction of all items noted by the Owner and Engineer after review of the documents.

B.The control system shall be guaranteed to be free from original defects in material and workmanship and in software design and operation for a period of one year after com- pletion of the contract. The Contractor shall provide the necessary skills, labor, and parts to assure that all system and component failures are promptly repaired.

C.The Contractor shall receive calls during the warranty period for all problems or questions experienced in the operation of the installed equipment and shall take steps to correct any deficiencies that may exist. The response time to critical problems shall be four (4) hours

maximum.

D.During the warranty period, the Contractor shall maintain a backup of all software installed in the system. The backup shall be updated monthly or whenever the Contractor makes a change to the software. A reload of backup software into the system shall be performed by

the Contractor immediately upon notification by the Owner. The reload shall be free of charge.

JANUARY 2008

UCCS STANDARDS

15950-10

Image 10
Contents Uccs Temperature Control Specifiers Guide Section Controls Part 1 General Special Conditions Work Included Definitions Drawings and SpecificationsSubmittal Data and Shop Drawings 15950-6 15950-7 Project Record Documents Demonstration and Training Warranty Quality Assurance Ownership of Proprietary MaterialPart 2 Products Manufacturers 15950-13 15950-14 Duct-mounted Uccs to add preferred manufacturer here 15950-16 AIR Tubing and Control Wiring Control Valves15950-18 Local Control Panels Compressed AIR Supply Pneumatic Actuators and Positioners Pneumatic 15950-22 15950-23 15950-24 SOLID-STATE Sensing Devices Transmitters Solid State15950-26 Auxiliary Devices Electric Actuators Electric Safety Controls Part 3 Execution CONTROL-AIR PipingControl Piping Liquids Control Wiring NET Controllers SCX 920 LCX 810, TCX 850, LCX 800I ALL Infinity ControllersInstallation and Setup Requirements 15950-34 Control Device Locations Control Panels IdentificationTesting CleanupProtection 15950-38 Control Execution General Workstation Programming 15950-41 DDC Software END of Section