scope of demolition is unclear, consult with Shop technician prior to bid submittal. Approval from HVAC/Controls must be given prior to bid submittal for waiver of demolition.
1.05DEFINITIONS
A.These specifications and drawings require finished work, tested, and ready for operation. Wherever the word "provide" is used, it shall mean "furnish and install complete and ready for use."
B."Contractor" shall mean the Controls Contractor performing work under this Division of the Specifications.
C.Where this specification states work to be performed by the words "shall" or "secure" or other performance functions, it shall be assumed that such work shall be performed by this Contractor unless stated otherwise.
D.The word "Mechanical" applies to all work specified herein wherever applicable.
E.The phrase "Architect/Engineer" implies that either may perform the task at hand.
F.The phrases "University Engineer" or "Owner's Representative" implies an assigned representative from the UCCS Facilities Management Department.
G.The term “UCCS HVAC Shop” implies a representative of the HVAC
shop of the University of Colorado at Colorado Springs.
1.06DRAWINGS AND SPECIFICATIONS
A.The mechanical drawings are diagrammatic in character and do not necessarily indicate every required offset, valve, fitting, etc.
B.All drawings relating to this structure, together with these specifications, shall be considered in bidding. The drawings and specifications are complementary, and what is called for in either of these shall be as binding as though called for by both. Should any conflict arise
between drawings and specifications, such conflict shall be brought to the attention of the Architect/Engineer for resolution.
C. Unless otherwise indicated, all equipment and performance data listed is for job site conditions (elevation 6,400 ft.).
D.Drawings are not to be scaled.
1.07SUBMITTAL DATA AND SHOP DRAWINGS
A. All shop drawings, I/O schedules, point lists, system schematics, sequences of operation,
JANUARY 2008 | UCCS STANDARDS |