7-INSTALLATION AND SET-UP (continued)

7.6Pneumatic & Control Board Connections (continued)

-Connect an air tube to the ON/OFF valve and attach it with a strap.

Minimum inside diameter of the tube 10mm; air pressure 6 BAR.

-Give air to the machine with the ON/OFF valve

(Figure 7-15).

Position the control board near the machine. Feeder cables: Connect the cable with multipolar connectors from the machine and from conveyor to the control board (Figure 7-16).

Front and back junction boxes connections (1, 2 - Figure 7-17 & 7-18):

800rf-NA

20

Figure 7-15

Figure 7-16

Figure 7-17

1

2

Figure 7-18