Frame Installation
7.Cutter Head Assembly. The Cutter head Assembly is shipped completely assembled with the Skid Shoe, Actuator
8. Install Cutter Bar Head Assembly Using
an over head hoist lift and slide the cutter bar assembly into place until the carriage arm is in alignment with the
9.Install The Hydraulic Tank Assembly. The hydraulic tank is shipped as an assembly with the filter and directional solenoid valve attached to it. The Hydraulic tank will bolt to the frame (See Item 4 Figure 1) with 4 bolts, lockwashers and Nuts (See Figure 1 & 7)
10.Make Certain Bolts are Tightened. Make certain that the mounting bolts so far are tight.
Figure 6
Figure 4
Carriage Arm Pin
Figure 5 | Carriage Arm Asy |
|
Carriage
Arm Pivot
Pin
| Tank | |
| Mounting | |
| Bolts | |
Figure 7 | ||
| ||
|
|
Switch Blade
© 2005 Alamo Group Inc. | Section 4 - 4 |