Carrier RVC, RVS, RDS006-060, RVR, RHR, RHS, 50RHC Field Power Supply Wiring, Field Control Wiring

Models: 50RHC RHS RVC RHR RVR RDS006-060 RVS

1 44
Download 44 pages 51.02 Kb
Page 18
Image 18
Step 8 — Field Power Supply Wiring

Step 8 — Field Power Supply Wiring

To avoid possible injury or death due to electrical shock, open the power supply disconnect switch and secure it in an open position during installation.

Use only copper conductors for field-installed electrical wiring. Unit terminals are not designed to accept other types of conductors. Failure to follow this safety precaution could lead to equipment damage.

All field installed wiring, including the electrical ground, MUST comply with the National Electrical Code (NEC) as well as applicable local codes. In addition, all field wiring must conform to the Class II temperature limitations described in the NEC.

Refer to unit wiring diagrams Fig. 19-22 for a schematic of the field connections, which must be made by the installing (or electrical) contractor. Refer to Tables 5-7 for fuse sizes.

Consult the unit wiring diagram located on the inside of the compressor access panel to ensure proper electrical hookup. The installing (or electrical) contractor must make the field connections when using field-supplied disconnect.

Operating voltage must be the same voltage and phase as shown in Electrical Data shown in Tables 5-7.

Make all final electrical connections with a length of flexi- ble conduit to minimize vibration and sound transmission to the building.

POWER CONNECTION — Make line voltage connection by connecting the incoming line voltage wires to the L side of the CC terminal as shown in Fig. 23. See Tables 5-7 for correct wire and maximum overcurrent protection sizing.

SUPPLY VOLTAGE — Operating voltage to unit must be within voltage range indicated on unit nameplate.

On 3-phase units, voltages under load between phases must be balanced within 2%. Use the following formula to deter- mine the percentage voltage imbalance:

% Voltage Imbalance

= 100 x

max voltage deviation from average voltage

 

average voltage

 

Example: Supply voltage is 460-3-60.

 

AB = 452 volts

 

 

 

BC = 464 volts

 

 

 

AC = 455 volts

 

 

 

Average Voltage =

452 + 464 + 455

 

 

3

 

 

 

 

 

=

1371

 

 

 

3

 

= 457

Determine maximum deviation from average voltage:

(AB) 457 – 452 = 5 v (BC) 464 – 457 = 7 v (AC) 457 – 455 = 2 v

Maximum deviation is 7 v. Determine percent voltage imbalance.

% Voltage Imbalance =

100 x

 

7

 

457

=

1.53%

 

This amount of phase imbalance is satisfactory as it is below the maximum allowable 2%.

Operation on improper line voltage or excessive phase imbalance constitutes abuse and may cause damage to electri- cal components.

NOTE: If more than 2% voltage imbalance is present, contact your local electric utility.

208-VOLT OPERATION — All 208-230 volt units are factory wired for 208 volts. The transformers may be switched to 230-volt operation by switching the red (208 volt) wire with the orange (230 volt) wire at the L1 terminal.

Step 9 — Field Control Wiring

THERMOSTAT CONNECTIONS — The thermostat should be wired directly to the Aquazone™ control board. See Fig. 19-22, and 24.

WATER FREEZE PROTECTION — The Aquazone control allows the field selection of source fluid freeze protection points through jumpers. The factory setting of jumper JW3 (FP1) is set for water at 30 F. In earth loop applications, jumper JW3 should be clipped to change the setting to 10 F when using antifreeze in colder earth loop applications. See Fig. 25.

AIR COIL FREEZE PROTECTION — The air coil freeze protection jumper JW2 (FP2) is factory set for 30 F and should not need adjusting.

ACCESSORY CONNECTIONS — Terminal A on the control is provided to control accessory devices such as water valves, electronic air cleaners, humidifiers, etc. This signal operates with the compressor terminal. See Fig. 26. Refer to the specific unit wiring schematic for details.

NOTE: The A terminal should only be used with 24 volt signals — not line voltage signals.

WATER SOLENOID VALVES — Water solenoid valves may be used on primary secondary pump and ground water installa- tions. A typical well water control valve wiring, which can limit waste water in a lockout condition is shown in Fig. 26. A slow closing valve may be required to prevent water hammer. When using a slow closing valve, consider special wiring con- ditions. The valve takes approximately 60 seconds to open (very little water will flow before 45 seconds) and it activates the compressor only after the valve is completely opened by closing its end switch. When wired as shown, the valve will have the following operating characteristics:

1.Remain open during a lockout

2.Draw approximately 25 to 35 VA through the “Y” signal of the thermostat.

IMPORTANT: Connecting a water solenoid valve can overheat the anticipators of electromechanical thermo- stats. Only use relay based electronic thermostats.

18

Page 18
Image 18
Carrier RVC, RVS, RDS006-060, RVR, RHR, RHS, 50RHC specifications Field Power Supply Wiring, Field Control Wiring