Chapter 3 Installing the Switch
Connecting Power to the Catalyst 4900M Switch
Connecting Power to the Catalyst 4900M Switch
Follow these steps and warnings when connecting power to the Catalyst 4900M switch:
Step 1 Prior to connecting the power supply to a power source, ensure that all of the site power and grounding requirements described in Chapter 2, “Site Planning,” have been met and the chassis is properly grounded as described in the “Grounding Requirements” section on page
Figure 3-5 Grounding Pad Location
232131
1
1
Grounding pad
Warning The
Step 2 Plug the power cords into the power supplies. Refer to Figure
|