Cisco Systems OL-7822-06 quick start Completing the Installation, Examining the LEDs, Final Tests

Models: OL-7822-06

1 64
Download 64 pages 28.48 Kb
Page 53
Image 53
Completing the Installation

C H A P T E R 6

Completing the Installation

This module discusses how to verify link connectivity and how to install a Service Control application.

Examining the LEDs, page 6-1

Final Tests, page 6-1

Viewing Configuration, page 6-2

Saving the Configuration Settings, page 6-3

Examining the LEDs

The GBE Link LED must be green to verify that an active connection exists.

The GBE Rx and Tx LEDs (if flashing green) indicate that traffic is being received or transmitted by the SCE 1000 platform, respectively.

Note that in an inline topology, the Rx and Tx LEDs indicate that packets are being received/transmitted by the SCE 1000 platform.

In optical splitter topologies, the Rx LEDs are the sole indicators. The Tx LEDs do not “blink”, since the Tx is not connected to the port in this topology.

Final Tests

The procedures for performing the final tests to verify that the SCE 1000 is functioning properly are explained in the following sections.

Verifying Operational Status, page 6-1

Viewing the User Log Counters, page 6-2

Verifying Operational Status

After all the ports are connected, verify that the SCE 1000 is not in a Warning state.

To verify that the SCE 1000 is not in a warning state, complete the following steps:

Step 1 On the SCE 1000 Front panel, examine that the Status LED is flashing green.

Cisco Service Control Engine 1000 2xGBE Quick Start Guide

 

OL-7822-06

6-1

 

 

 

Page 53
Image 53
Cisco Systems OL-7822-06 Completing the Installation, Examining the LEDs, Final Tests, Verifying Operational Status