Section 3 • Installation
Foundation | Foundation Materials | ||
Materials needed to build the foundation are forms, | |||
Vilter Single Screw compressor units are low vibra- | |||
concrete, sand, rebar, wire, grout, anchor bolts, ex- | |||
tion machines. Under most conditions, no elaborate | |||
pansion board and shims. A set of concrete forms will | |||
foundation is necessary. However a sound foundation | |||
need to be acquired; generally, these can be rented or | |||
maintains motor alignment and proper elevation, and | |||
constructed from dimensional lumber. There should | |||
is therefore required. Provided are recommendations | |||
be enough 4,000 psi concrete with one inch aggregate | |||
for the foundation and anchoring of the compressor | |||
to build the foundation. Also, there should be enough | |||
unit. The Vilter foundation supports the entire operating | |||
sand to provide a base of compacted sand four inches | |||
weight of the unit and is suitable for years of continuous | |||
thick for the foundation to rest on, see Figure 1 - Con- | |||
duty. Included are specifications for concrete, rebar, ag- | |||
crete Pad with Compressor Unit Dimensions - Side | |||
gregate, anchors and grout. | |||
View. The rebar required is ASTM 615, grade 60, sizes | |||
|
| ||
Considerations Prior to Starting | #4 and #6. Wires will also be needed to tie the rebar | ||
together. The recommended grout is Masterflow 648CP | |||
Consult professionals, such as building inspectors, | high performance | ||
structural engineers, geotechnical engineers and/or | a 1” thick pad under each foot. The recommended an- | ||
construction contractors prior to starting. Below are a | chors are 5/8” Diameter HILTI HAS SS threaded rod for | ||
few points to consider: | outdoor installations or | ||
|
| tions. Anchor bolts shall have a five inch projection and | |
Site Characteristics: | |||
• | Soil information | HIT/HY 150 anchoring system. There should be enough | |
• | Site drainage | one inch expansion boards to go around the perimeter | |
of the foundation. Finally there should be enough shim | |||
• | Wind data | ||
stock and extra anchor bolt nuts to level the compres- | |||
• | Seismic zone | sor unit. | |
| |||
• | Ingress and egress | Building the Foundation | |
• Power and power lines | |||
Use the Vilter General Arrangement (GA) and founda- | |||
|
| ||
|
| tion drawings to help secure a building permit and | |
Site Layout: | foundation construction. The Vilter GA drawing will | ||
• Plant elevations, grading, drainage and erosion | have the necessary dimensions required to determine | ||
• Accessibility to compressors for service | the overall foundation size and where to locate the | ||
compressor unit on the foundation. It will also show the | |||
• Location of surrounding buildings | |||
dimensions required to form up the housekeeping piers | |||
• Property lines and roadways | that the compressor unit rests on. The Vilter foundation | ||
• | Power | drawing lists the necessary information to construct a | |
suitable foundation. It includes the rebar requirements | |||
• | Fire safety | ||
and locations. It also shows anchor bolt locations, | |||
|
| grouting and the concrete specifications. Using the | |
Safety: | Vilter GA drawing, Vilter foundation drawing and the | ||
information from site characteristics, site layout and | |||
| NOTE | ||
| safety studies will provide enough data to allow build- | ||
Always check with a safety engineer before proceeding. | |||
ing the foundation to proceed. | |||
|
| ||
• Arranging equipment with adequate access space for | The foundation is to be cast and permanently exposed | ||
| safe operation and maintenance | ||
| against the earth. Therefore, if constructing on an exist- | ||
• | Wherever possible, arrange equipment to be served | ||
ing floor, typically indoors, the floor will need to be bro- | |||
| by crane. If not feasible, consider other handling | ||
| ken up to get to the earth. If starting from undisturbed | ||
| methods | ||
| soil, it must be also be prepared accordingly. In either | ||
|
| ||
• Make all valves and devices safely accessible | case, these are some check points to consider: | ||
• Use special bright primary color schemes to differen- | • Check the depth of your frost line to ensure | ||
| tiate service lines | ||
| the foundation extends below it | ||
• Lightening protection for outdoor installations | |||
• Ensure the foundation rests entirely on natural rock | |||
• | Relief valve venting | ||
or entirely on solid earth, but never on a combination |
VSG/VSSG • Installation, Operation and Maintenance Manual •Vilter/Emerson • 35391SSG | 3 – 5 |